Re: protection password - How to remove it form a 2007 Project Fil

Tech-Archive recommends: Fix windows errors by optimizing your registry



Hello Justin,

Okay, obviously I'm not following you completely. You have a Project
2003 file with a write-protection password. Do you know what the
password is? If you don't know the original password you cannot
remove it either using Project 2007 or Project 2003.

If you know the write reservation password then removing the **** in
the manner I noted below will remove the password, but if you can't
open the file read-write without the password, there is not a method
to remove it.


I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"Dytham" <Dytham@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:A51E2223-36BF-4528-BD86-D499C8C8072E@xxxxxxxxxxxxxxxx
I'm using Project 2007 with SP1 and have not found a way to SaveAs
either as
original filename or new file name without either original
protection
password or a newly supplied one.

Deleting the ******* in General Options only succeeds in the saved
file
retaining the original protection password.

"JulieS" wrote:

Hello Justin,

In order to remove the password from the file, you'll need to open
the
file. *******Make a copy of the file before attempting the next
steps
and make sure you have SP-1 installed on Project 2007*****
Open the file, supplying the password.
In Project 2007, choose File > Save As to open the Save As dialog.
Click the Tools button in the lower left corner of the Save As
dialog
box and select "General Options".
Click and drag to select all marks (*****) in the protection and/or
write reservation password area.
Save the file with the same name and choose to overwrite the
original
file.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project

"Justin" <Justin@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:CA5F755E-088C-473A-BE17-34A674697A7D@xxxxxxxxxxxxxxxx
I am trying to un-password a file that was created in Project
2003.
We
recently upgraded to Project 2007. This password was to block
other
users
from changing the file and to allow access to the file. Any
input
would be
appreciated.





.