RE: BCWP and BCWS



Might be a couple of things:

1) Set the Status Date in Project > Project Information
2) Make sure that the task Earned Value calculation is set to % Complete
(which is the default). I think that's Tools > Options > Calculations, but
on existing tasks, you have to expose the field, which is Earned Value Method
3) If you're using Project 2007, make sure that you have the Service Pack
installed. There were apparently some issues w/ exporting EVMS data before
that was released.

Probably the first one will work though.

-A

"Anna" wrote:

I saved a baseline and I entered my planned cost in BAC field and enetered %
complete and the BCWP field still shows 0 value. What am I doing wrong?
.



Relevant Pages

  • RE: task start date changes when I update task
    ... In Project> Project Information, check the Status Date. ... You might also want to look at Tools> Options> Calculation, ... > done that is causing this. ... > effecient method. ...
    (microsoft.public.project)
  • RE: BCWP and BCWS
    ... tables/more tables/earned value to check and see if the BCWP and BCWS ... Make sure that the task Earned Value calculation is set to % Complete ... There were apparently some issues w/ exporting EVMS data before ... complete and the BCWP field still shows 0 value. ...
    (microsoft.public.project)
  • Re: Enterprise Fields
    ... Try posting on the server newsgroup as this one is closing down. ... FAQ Item: 24. ... Project information can be seen at this web ... The calculation used in the second ...
    (microsoft.public.project.pro_and_server)