RE: BCWP and BCWS
- From: Andrew Lavinsky <Andrew Lavinsky@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Sat, 3 May 2008 05:44:00 -0700
Might be a couple of things:
1) Set the Status Date in Project > Project Information
2) Make sure that the task Earned Value calculation is set to % Complete
(which is the default). I think that's Tools > Options > Calculations, but
on existing tasks, you have to expose the field, which is Earned Value Method
3) If you're using Project 2007, make sure that you have the Service Pack
installed. There were apparently some issues w/ exporting EVMS data before
that was released.
Probably the first one will work though.
-A
"Anna" wrote:
I saved a baseline and I entered my planned cost in BAC field and enetered %.
complete and the BCWP field still shows 0 value. What am I doing wrong?
- Follow-Ups:
- RE: BCWP and BCWS
- From: Anna
- RE: BCWP and BCWS
- References:
- BCWP and BCWS
- From: Anna
- BCWP and BCWS
- Prev by Date: Re: SQL backup
- Next by Date: RE: % Complete to Date
- Previous by thread: BCWP and BCWS
- Next by thread: RE: BCWP and BCWS
- Index(es):
Relevant Pages
|