Re: Predecessor and Task finish dates don't shift dependant start dates?



On Apr 8, 12:59 pm, "Jan De Messemaeker" <janremovet...@xxxxxxxxxxx>
wrote:
Hi,

The percentages make a bell ring.
Once you neter Actual dat especially actual start (which i automatically set
when entering a %complete not zero) dependencies will not move the task.
Actual data should be a reflexion of past history and Project won't change
that
HTH


I grabbed this project as a template. When I first starting tweaking
start dates, all dates were rolling. At some point they stopped. I
only want the % as informational. Now what?

Thanks.
.