Re: Predecessor and Task finish dates don't shift dependant start dates?
- From: wildman@xxxxxxxxxxxx
- Date: Tue, 8 Apr 2008 11:08:32 -0700 (PDT)
On Apr 8, 12:59 pm, "Jan De Messemaeker" <janremovet...@xxxxxxxxxxx>
wrote:
Hi,
The percentages make a bell ring.
Once you neter Actual dat especially actual start (which i automatically set
when entering a %complete not zero) dependencies will not move the task.
Actual data should be a reflexion of past history and Project won't change
that
HTH
I grabbed this project as a template. When I first starting tweaking
start dates, all dates were rolling. At some point they stopped. I
only want the % as informational. Now what?
Thanks.
.
- Follow-Ups:
- Re: Predecessor and Task finish dates don't shift dependant start dates?
- From: Jan De Messemaeker
- Re: Predecessor and Task finish dates don't shift dependant start dates?
- References:
- Predecessor and Task finish dates don't shift dependant start dates?
- From: wildman
- Re: Predecessor and Task finish dates don't shift dependant start dates?
- From: Mike Glen
- Re: Predecessor and Task finish dates don't shift dependant start dates?
- From: wildman
- Re: Predecessor and Task finish dates don't shift dependant start dates?
- From: wildman
- Re: Predecessor and Task finish dates don't shift dependant start dates?
- From: Mike Glen
- Re: Predecessor and Task finish dates don't shift dependant start dates?
- From: wildman
- Re: Predecessor and Task finish dates don't shift dependant start dates?
- From: Jan De Messemaeker
- Predecessor and Task finish dates don't shift dependant start dates?
- Prev by Date: Re: Portfolio Server Attribute Mapping Configuration Error
- Next by Date: Re: Predecessor and Task finish dates don't shift dependant start dates?
- Previous by thread: Re: Predecessor and Task finish dates don't shift dependant start dates?
- Next by thread: Re: Predecessor and Task finish dates don't shift dependant start dates?
- Index(es):
Relevant Pages
|
|