Re: Differences in Task types



Fixed task types only have an effect when you edit an assignment. Units always = Work / Duration

So, Edit one, fix one and the third one gets recalculated.

You fix one by selecting the relevant Task type.

So, you need to add more work but the assignment mustn't take any longer? Edit the Work, fix the duration and the units get recalculated when you click OK: easy!

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com



"Sondin" <Sondin@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message news:4D6CECE5-9BE1-452F-A254-8A213187D90F@xxxxxxxxxxxxxxxx
Can anyone enlighten me on the differences in task types with a clear
example? I am still confused between Fixed units, Fixed duration and Fixed
work when setting my tasks.

Thanks.

.



Relevant Pages

  • Re: Using Task Types
    ... units always =work / duration ... So edit one of the three, fix one of the three and the third one is calculated. ... It is therefore impossible to fix two and edit the third because the formula would then break which can't happen. ... Author of the only book on Project VBA, ...
    (microsoft.public.project)
  • Re: Fixing Start AND End Dates of tasks
    ... You really can't fix both start and end directly. ... making the task a fixed duration task and fixing the start date with a "Must ... to meet those dates and if the initial calculation says no, ...
    (microsoft.public.project)
  • Re: Access 2k3
    ... > any of them to edit produces nothing. ... > reinstalled office 2k3 and it does not fix the problem. ... > Both my desktop pc and laptop have WinXP Pro with all SP's and hotfixes ...
    (microsoft.public.access.setupconfig)
  • Re: protect duration and work
    ... You cannot fix two of them. ... the Duration is the critical value and then lock it. ... If you lock Duration and you change Work, ... and the Task Type can be either Fixed ...
    (microsoft.public.project.pro_and_server)
  • Re: How do I set up a fixed duration AND fixed work schedule and h
    ... I should be able to specify a fixed Duration (a specific start ... and have MS Project only recalculate just the Effort. ... Whichever of the remaining 2 terms you edit ... > initial resource assignment (duration, work and effort all have to be there ...
    (microsoft.public.project)