Re: Default Task Type

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance



Changes to the schedule don't mean it's failed. But a project plan that a) finishes late; b) finishes over budget; c) fails to meet chartered scope; or d) is abandoned prior to completion certainly is. While scope changes certainly occur and by themselves don't necessarily mean failure, they should be driven by changing business needs or a changing economic environment and not by scheduling or budgetary conditions within the project. The whole reason for using a scheduling tool is so we are better able to devise a plan that will have us finishing on-time and within budget WITHOUT having to compromise on scope or quality and one that is solidly enough grounded in reality that we'll actually be able to work the plan as scheduled in practice.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://project.mvps.org/faqs.htm for the FAQs


"Jack Dahlgren" <jack@xxxxxxxx> wrote in message news:%234IfpXuiIHA.5780@xxxxxxxxxxxxxxxxxxxxxxx

....>> I know that scope tradoffs happen in software development (and
elsewhere) - that doesn't mean they're good.

Changes to a plan in response to reality are inevitable and are neither bad nor good.

.....

The schedule tool doesn't know if a change is good or bad either. I hope you aren't suggesting that a schedule is failed if there is any change to it. Changing your "reality" to match your plan is not a particularly good idea.

-Jack Dahlgren


.



Relevant Pages

  • Re: Getting Started: I have an idea of how I want to setup my proj
    ... to budget and within the deadlines. ... the first pass of the plan is not within budget or schedule, ... We have a set number of dollars and a firm deadline. ...
    (microsoft.public.project)
  • Re: Default Task Type
    ... Exactly - my point is more what happens after the initial estimate - as one does "what-if" cases to build a workable plan to best meet the project's objectives, should one lock down the duration to the initial estimate and have the work estimate change for each revision in resource assignment or does it make more sense to lock down the work estimate that Project has initially calculated and have the duration change as we experiment with different resource assignments? ... I reiterate my objection to fixed duration - it's often used to try to force the project schedule to conform to some preceived notion of what it ought to look like - management as an act of imposition of will power - rather than going through the process of discovery of a working model that can be used to accurately predict outcomes. ... While scope changes certainly occur and by themselves don't necessarily mean failure, they should be driven by changing business needs or a changing economic environment and not by scheduling or budgetary conditions within the project. ...
    (microsoft.public.project)
  • Re: Getting Started: I have an idea of how I want to setup my proj
    ... Or, given the assignments required/planned by the task and input to Project, Project can compute the cost to and you can look if it is above or below budget. ... If the first pass of the plan is not within budget or schedule, ... I would like to be able to use project to see how many people it will take to get my project finished by the deadline. ...
    (microsoft.public.project)
  • Re: Default Task Type
    ... In my opinion they are a valid and useful way of modeling a schedule. ... scope; or d) is abandoned prior to completion certainly is. ... plan as scheduled in practice. ... Changes to a plan in response to reality are inevitable and are neither ...
    (microsoft.public.project)
  • Re: Getting Started: I have an idea of how I want to setup my project,
    ... Use Project to develop schedules which become a map for how to execute the project to budget and within the deadlines. ... If the first pass of the plan is not within budget or schedule, ...
    (microsoft.public.project)