RE: Resource Allocation
- From: Jim Aksel <JimAksel@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Thu, 20 Mar 2008 20:06:01 -0700
Here's one method, but it is not recommended.
You would need to put a long duration task on one line implying all the
activities in the name:
Create 1500 sq m concrete Module
duration 20 days (or whatever). Assign resources as needed. Open the Task
Usage View and manually re-key the worker effort to the days desired. You
may need to use fixed duration as the task type.
Suggestion: Make a "module" of the tasks. Indent all the subtasks needed
under a heading which will make it a summary. Assign resources as required
to appropriate subtasks
--
If this post was helpful, please consider rating it.
Jim
Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
"tough1857" wrote:
I have to allocate a resource which is different that the normal ones..
Slab forms - This is a set of forms which:
1. Required 3 days for installation
2. Beyond these 3 days, other activities like reinf binding & casting
needs to be done
3. After the casting activity, the concrete cast needs to attain
strength - 7 days after casting
4. Then these forms can be dismanatelled and reused
I need to allocate resource for this - say a set of 1500 sqm.
How do i do this by having a single task
- References:
- Resource Allocation
- From: tough1857
- Resource Allocation
- Prev by Date: RE: Microsoft project 2003
- Next by Date: Favourite Books
- Previous by thread: Resource Allocation
- Next by thread: Re: Adding a new Group By for the Opening a Project
- Index(es):
Relevant Pages
|