RE: Resource Allocation



Here's one method, but it is not recommended.

You would need to put a long duration task on one line implying all the
activities in the name:

Create 1500 sq m concrete Module

duration 20 days (or whatever). Assign resources as needed. Open the Task
Usage View and manually re-key the worker effort to the days desired. You
may need to use fixed duration as the task type.

Suggestion: Make a "module" of the tasks. Indent all the subtasks needed
under a heading which will make it a summary. Assign resources as required
to appropriate subtasks


--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project



"tough1857" wrote:

I have to allocate a resource which is different that the normal ones.

Slab forms - This is a set of forms which:
1. Required 3 days for installation
2. Beyond these 3 days, other activities like reinf binding & casting
needs to be done
3. After the casting activity, the concrete cast needs to attain
strength - 7 days after casting
4. Then these forms can be dismanatelled and reused

I need to allocate resource for this - say a set of 1500 sqm.

How do i do this by having a single task

.



Relevant Pages

  • Re: What should be put into a duration?
    ... the availability of the resources required to do the work. ... usually assign a resource at 100% - if Bob is assigned to wax widgets I'm ... So when I input the task I'm going to estimate its duration and let Project ... the training should be split out as individual tasks in their own ...
    (microsoft.public.project)
  • Re: Isnt there a "Machine" Resource Type???
    ... I may also have to go back and fix the duration ... The answer is there is only ONE CLASS used for allocated resources, ... Fixed units, fixed work, and fixed duration only applies to what happens ... SCHEDULE these d_mn tasks. ...
    (microsoft.public.project)
  • Re: Estimated dates
    ... Now your problem is figure out exactly HOW to achieve those objectives - what workflow organization and what sorts of resources and how many to assign where will be required in order for it to be possible for these tasks to take place where they must take place in order for your project to be successful. ... I have a set schedule that I need to stick to based on outside ... I can in fact think of tasks that could have a flexible duration - that could ... Than or a Finish No Earlier Than constraint date (bet you have a little ...
    (microsoft.public.project)
  • Re: Isnt there a "Machine" Resource Type???
    ... to resources on a task, I may also have to go back and fix the duration ... assignments" checkbox is turned OFF, ... by leveling when resources are overallocated) and suspensions (the ... Leveling never changes the amount of a resource's work nor the duration ...
    (microsoft.public.project)
  • Re: Isnt there a "Machine" Resource Type???
    ... I may also have to go back and fix the duration ... The answer is there is only ONE CLASS used for allocated resources, ... Fixed units, fixed work, and fixed duration only applies to what happens ... scheduling scenario and this post is getting more detailed than I have ...
    (microsoft.public.project)