Re: Baseline Revision
Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance
- From: "Steve House" <sjhouse at hotmail dot com>
- Date: Thu, 20 Mar 2008 08:31:49 -0400
You can select all the tasks from the change point forward and in the Save
Baseline dialog box choose "Selected Tasks" instead of "Entire Project."
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
"Laz" <Laz@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:62906B7B-36D7-4311-A33E-937BF670F7C0@xxxxxxxxxxxxxxxx
We use our MS project plan to compare the progress of the project relative
to
the original plan, the baseline. We need to make a modification to the
original plan. We need to change the sequence of tasks but the individual
tasks and durations for the baseline we want to keep the same.
We have already started the project, but the tasks that we are going to
"re-sequence" have not started yet. I just modified the predecessors and
successors but the dates did not change. I though MS Project would
calculate
the new dates, I even manually did a "Calculate Now". No change. I set a
new baseline but the duration of the tasks already worked on changed
therefore my overall schedule and completion date changed.
I want to set a new baseline using the original durations not taking into
consideration the progress on the project. How do I do this?
.
Relevant Pages
- Re: new project dates to auto fill
... > like to be able to enter a start date (baseline) and according to the ... estimated Durations and inter-dependencies between tasks. ... Once your plan is as you want it (i.e. all necessary tasks are included ... to achieve the end goal, usually some completion milestone, and the ... (microsoft.public.project) - Re: updating a project tasks and durations
... You save the baseline after the plan is finalized as a reference against which you track progress. ... So if you start with a generic template any baseline associated with it is meaningless and should be discarded as that doesn't represent the "real" project plan you will be working. ... You customize the plan, dropping tasks that are unnecessary due to differences in scope between this plan and the template it's based on, adding other tasks if required, estimate durations for individual tasks Then after the plan is approved and before any work is performed, you create the baseline so you'll later be able to measure actual performance against the plan you envisioned so you can tell if you're on-time or not and are staying within your budget. ... (microsoft.public.project) - Re: statistical graph showing percentages
... predicted task durations (baseline). ... "predicted task durations" and how that relates to task completions. ... The first filter would find all tasks that are between month ... (microsoft.public.project) - Re: Baseline
... We use our MS project plan to compare the progress of the project relative ... to the original plan, the baseline. ... work out of sequence, or changing the sequence. ... The individual tasks and durations for the baseline we ... (microsoft.public.project) - Re: Baseline
... If you've extensively changed the link relationships, ... Generally what I am trying to discover when comparing baseline to actual ... are variances from the original plan against changes made in the process ... (microsoft.public.project) |
|