Re: Leveling Changes work hours from 2 hrs to 14,944

Tech-Archive recommends: Fix windows errors by optimizing your registry



Hi Steve,

Welcome to this Microsoft Project newsgroup :)

Have you installed SR1? Incidentally, all levelling does is to delay tasks
until the resources are available - nothing else.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials



"Steve" <Steve @discussions.microsoft.com> wrote in message
news:46A02DB0-E728-4710-92D6-1DD0B115620F@xxxxxxxxxxxxxxxx
Hi: I'm seeing a similar behavior in 2007 Project Pro, but w/o Enterprise
server. When I manually level my project, I get some tasks in which the
work
is recalculated from xx hours to yy,yyy hours. This must be a bug
(right?).
I'm new to leveling, but I thought that task work should always remain the
same and it's the duration that may change?

-Steve


"Mike Glen" wrote:

Hi Barb,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project
information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP


Barb K wrote:
I have a project that was created in 2007 Project Pro and saved
locally. I imported the project onto the Enterprise server. Now I
want to do some updates. I retrieved the project from the enterprise
server and have all of my work hours. All tasks have the same
resource on all of them. There are many tasks that start on the same
day. When I level the resources I have one task that was 2 hrs of
work is now 14,944 hours and one other that was 8 hrs is now 73,119
hrs. I have not had this problem with projects that were created and
saved directly on the enterprise server.

Has anyone encountered this problem?





.



Relevant Pages

  • Re: Cannot access resources in PWA
    ... Victoria wrote: ... Try posting on the server newsgroup. ... ocurred while trying to access the resources stored on the database. ...
    (microsoft.public.project)
  • Re: Updating via timesheet
    ... Fair comment, Dale, but I burned my fingers in the past commenting on ... Project when using a server because I did not know the ramifications ... I now always suggest using the correct newsgroup just in case:( ... the resources adjust both actual and remaining ...
    (microsoft.public.project)
  • Re: Email enable doc lib
    ... server to test the issue. ... Microsoft CSS Online Newsgroup Support ... This newsgroup only focuses on SBS technical issues. ... Please try to logon Public folder list using URL: ...
    (microsoft.public.windows.server.sbs)
  • Re: R2 w/ISA User type account cannot use my companys internal website
    ... can refer to the steps below to reinstall the SBS Monitoring component. ... Select Windows Small Business Server 2003 and then click Change/Remove. ... select Microsoft SQL Server Desktop Engine ... Microsoft CSS Online Newsgroup Support ...
    (microsoft.public.windows.server.sbs)
  • Re: Email enable doc lib
    ... Microsoft CSS Online Newsgroup Support ... This newsgroup only focuses on SBS technical issues. ... navigate to the public folder and send some posts with attachments to the ... I have disabled forms base Athentication from the default V.Smtp server ...
    (microsoft.public.windows.server.sbs)