Re: Project 2007 - Resource Calendar
- From: "Mike Glen" <glenATmvps.org>
- Date: Tue, 5 Feb 2008 14:57:24 -0000
Hi Julie,
Yes, here:
https://connect.microsoft.com/feedback/ViewFeedback.aspx?FeedbackID=327241&SiteID=235
Mike
"JulieS" <passport6847 at maine dot rr dot com> wrote in message
news:uSIdVr$ZIHA.1164@xxxxxxxxxxxxxxxxxxxxxxx
Thanks Mike. Did you drop it on the Project 2007 connect site, if so,
I'll chime in with a "can reproduce" on the site.
Julie
"Mike Glen" <glenATmvps.org> wrote in message
news:#orhPg$ZIHA.1532@xxxxxxxxxxxxxxxxxxxxxxx
I've submitted this as a bug.
Mike Glen
Project MVP
"Steve C." <SteveC@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:CC8ABDBE-CBCA-45CA-9A3D-3B24FB6AC413@xxxxxxxxxxxxxxxx
Hi Jan,
Then it must be how we have our machines configured since it is
hapeening on
several different machines in our office. Time to start from scratch.
Thanks again!
Steve
"Jan De Messemaeker" wrote:
Hi,
Gone through the motions again, exactly as you write, no problem.
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Steve C." <SteveC@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:676C87EA-5F8D-4AD1-8D33-A778F59CA73D@xxxxxxxxxxxxxxxx
Mike, Jan,
Thanks for the feedback. Here is what I am doing:
Launch Project. Set 2/18/08 as a Holiday in the Standard Calendar.
Switch
to
Resource *** view and add a new resource "Resource 1". Open the
calendar
for "Resource 1" and select the WorkWeek tab. In the row below the
default
enter "45 Hr. Work Week". The "Start" date defaults to today's date
and
make
the "Finish" date whatever you wish - While entering this reply I
entered
3/31/08. Select "Detail" and highlight Monday thru Friday. Change the
"To"
time from 5:00PM to 6:00PM. Then select the last radio button to set
the
days
to the new working times. Close the details window. Now select
several
dates
to verify the new working time has been set for the dates selected,
days
outside of the range are the standard working time, weekends are
still
non-working days, and 2/18/08 is also a non-working day. At some
point the
program stops responding and crashes. Sometimes right away. Other
times it
takes a few minutes.
Steve
"Jan De Messemaeker" wrote:
Hi,
I have 2007 Pro, not Server, installed and I cannot reproduce the
problem.
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Mike Glen" <glenATmvps.org> wrote in message
news:Ob9wWpzYIHA.1132@xxxxxxxxxxxxxxxxxxxxxxx
Hi Steve,
I'm using Project Standard 2007 and cannot get the crashes you've
experienced. Perhaps someone using 2007 Pro in a stand alone
situation
without a server can take this on board?
Mike Glen
Project MVP
"Steve C." <SteveC@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:7135B74F-9B76-4E28-B206-71CA7B3821DA@xxxxxxxxxxxxxxxx
Hi Mike,
Sorry for not being clear. I initially came across this problem
using
project schedule we created for our 2003 class (reentering the
data of
course
so we can capture new screen shots). However, since that time two
of
my
colleagues get the same result on thier machines using the blank
project
that
opens when you launch Project. Simply create a resource and
modify
their
resource calendar. Don't even add a task.
Steve
"Mike Glen" wrote:
But your project may be corrupt! Did you try it with a new
project?
If
so,
and it still crashes, perhaps you could send it to me to have a
look
at.
Mike Glen
Project MVP
Steve C. wrote:
Hi Glenn,
I will take a look at FAQ item 43. We have tried it on
different
PCs
and laptops with consistant results. Just add a new resource
and
add
one WorkWeek item in the next available line under the default
line.
If it does not crash right away scroll through that resource's
calendar (change months) and it will.
Since we all use the same PC/laptop manufacturer here in the
office
I
think I may try installing an eval copy at home to see if it
happens
on my Dell. Try it yourself and let me know what happens.
Thanks.
"Mike Glen" wrote:
Hi Steve,
Try again with a new project and see if it still crashes. If
it
doesn't, I would suspect a currupt file. You could try the
suggestions in FAQ Item:
43. Handling project file corruption and/or bloat.
FAQs, companion products and other useful Project information
can
be
seen at this web address:http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :-)
Mike Glen
Project MVP
Steve C. wrote:
Hi Mike - Thanks!
I am using Project 2007 Professional. Yes. SP1 is installed.
No.
I
am not using Project Server yet. I am actually working on a
MS
Project 2007 training course and came across this problem
while
creating slides for using the new resource calendar
features.
"Mike Glen" wrote:
Hi Steve,
Welcome to this Microsoft Project newsgroup :)
Which version of 2007 are you using? Have you got SR1
installed?
Are you using Project Server?
FAQs, companion products and other useful Project
information
can
be seen at this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
Steve C. wrote:
Project 2007 crashes when I setup a special "WorkWeek"
calendar
for a resource. Sometimes it crashes right away. Sometimes
it
takes a few minutes. If I use the "Default" line on the
"WorkWeek" tab Project 2007 does not crash. This happens
on 3
different PCs/laptops in my office. Has anyone run into
this
problem? Suggetions?
.
- Follow-Ups:
- Re: Project 2007 - Resource Calendar
- From: JulieS
- Re: Project 2007 - Resource Calendar
- References:
- Re: Project 2007 - Resource Calendar
- From: Mike Glen
- Re: Project 2007 - Resource Calendar
- From: JulieS
- Re: Project 2007 - Resource Calendar
- Prev by Date: Re: Need Simple Gantt chart
- Next by Date: Re: View Table Name
- Previous by thread: Re: Project 2007 - Resource Calendar
- Next by thread: Re: Project 2007 - Resource Calendar
- Index(es):