Re: Showing Task Progress at a summary level project on the Gantt Char
- From: "Jan De Messemaeker" <janremovethis@xxxxxxxxxxx>
- Date: Wed, 23 Jan 2008 18:42:36 +0100
Hi,
IN Bar Styles (Format,Bar Styles) add the following line:
Name... Summary Progress
Appearance: select (lower half bar, full, blue)
show for: Summary
from Start
To Complete Through
OK.
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"PK Consulting" <PKConsulting@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:31BDFE88-AA69-438E-B3FC-36B9EF84F41B@xxxxxxxxxxxxxxxx
MS Project 2003 - Standard.
Is there a way to show the progress bar (usually blue) at the summary
level?
For example, I have a summary task that has three sub-tasks. I'd like to
roll-up the summary task to one line and print a Gantt with the planned
and
progress (blue).
Thank you in advance for your help.
Paul Peterson
.
- Prev by Date: Re: Master schedules
- Next by Date: Re: Accept or reject levelling
- Previous by thread: Re: Export tasks and resources with timsescaled data
- Next by thread: Can increase durations "automatically" to meet a new project expected finish date?
- Index(es):
Relevant Pages
|