Hi Melpina,

Next time, please post on the server newsgroup. Please see FAQ Item: 24.
Project Newsgroups. FAQs, companion products and other useful Project
information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP



"Melpina" <Melpina@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:38D04EEB-DBF0-45B5-86BA-488F7FA7DFE1@xxxxxxxxxxxxxxxx
I am using Project 2003 and was shocked to see that in the resource usage
page all of my resources were red indicating that they were over
allocated.
Upon further investingation I found that the availability dates for some
resources were set for 1 year and some were set at N/A. Is this a default
setting? Do I have to go back every year and change this or is there a
way
to change it and make it open ended? PS In case it makes a difference my
resources are coming from the enterprise resource pool.


.



Relevant Pages

  • Re: Resource Substitution Wizard Across Mulitple Projects
    ... Please see FAQ Item: 24. ... Project Newsgroups. ... able to do them faster if I am smart with substituting resources - but I ... can't the Substitution Wizard take over allocation into account? ...
    (microsoft.public.project)
  • Re: Project Web Access 2007: Views
    ... Try posting on the server newsgroup as this one is closing down. ... FAQ Item: 24. ... Project Newsgroups. ... This post is a suggestion for Microsoft, ...
    (microsoft.public.project.pro_and_server)
  • Re: Force zeros instead of blank entries in user timesheets
    ... Try posting on the server newsgroup as this one is closing down. ... FAQ Item: 24. ... Project Newsgroups. ... companion products and other useful ...
    (microsoft.public.project.pro_and_server)
  • Re: Group By Sorting
    ... Try posting on the server newsgroup as this one is closing down. ... FAQ Item: 24. ... Project Newsgroups. ... I have suggested to Microsoft adding "Sort Field" options under ...
    (microsoft.public.project.pro_and_server)
  • Re: Work Calculation Error with Multiple Resources
    ... Please see FAQ Item: 24. ... Project Newsgroups. ... example, the task below is effort driven, and has 3 resources working on it, ... This is certainly effecting our resource allocation calcuation roll-up. ...
    (microsoft.public.project)