Re: Fractional Durations in Summary Tasks

Tech-Archive recommends: Fix windows errors by optimizing your registry



Hi,

Also read FAQ 5 which handles this quiestion in:
http://www.mvps.org/project/faqs.htm

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"DanD" <DanD@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:304D290A-AC9A-4197-9C08-7F5F125DACD0@xxxxxxxxxxxxxxxx
I have just started using MS Project and I am having a problem with
fractional totals showing up in the summary tasks even though I have been
working in whole or half days. I would expect thhe durations to be either
whole numbers or with a extra 0.5 . Instead I end up with durations like
5.167 or 3.875.

I have looked for readily apparent problems but I used only whole or 0.5
days for durations and all resources are 100 percent commited. I can go
back
throuugh the individual task and find the fractions but have no idea how
they
changed away form what I had entered.

Thank you for any help with this.



.



Relevant Pages

  • Re: Fractional Durations in Summary Tasks
    ... fractional totals showing up in the summary tasks even though I have been ... I would expect thhe durations to be either ... or on the Resource Usage view if a resource's ... working time is causing the odd hours. ...
    (microsoft.public.project)
  • Re: how to calculate the sum of durations of subtasks for a summar
    ... summary tasks and other tasks. ... > Thanks Rod. ... >> Visit www.msproject-systems.com for Project Companion Tools and more ... >>> of subtasks's durations, not the longest duration for their ...
    (microsoft.public.project.vba)
  • Re: CHANGING DATES & DURATION IN A HEADING
    ... The durations of Summary tasks, e.g. the start/end dates will ... > formed groups with headings using the indent arrow. ...
    (microsoft.public.project)
  • durations problem?
    ... i have problem with durations ... but while i change them the summary tasks are ... in week & subtasks in day & when i change them to week ...
    (microsoft.public.project.standard_and_server)
  • Re: Project Summary Task Durations
    ... Rollup of durations is calculating the difference between first start and ... Summary tasks followed by subtasks. ... calculating my summary task durations. ...
    (microsoft.public.project)