Re: Master schedules
- From: John <mjensen@xxxxxxxxxxxx>
- Date: Tue, 22 Jan 2008 20:19:26 -0700
In article <BA022AB5-ED59-4B21-A149-F1C0A9020F93@xxxxxxxxxxxxx>,
DavidC <DavidC@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:
Hi,
I have a project made up of 14 separate files. These files cover three of
our contractors, four of their contractors, and seven files relating to our
own work fronts. To keep the history, I make a copy of the folder containg
all the files and rename it with a unique name.
I work over a network with the folder kept on a server, but as I work on
site as well and do not always have access to the server, I have
synchronised the relevant folders including the folders for my schedule.
What I find is that the external links seem not always to update to the new
folder name, but rather retain the link to a file in an older folder which is
found on the server.
Is there a fix for this or any work around that anyone has found? At
present the only work around that seems to work after a fashion, is to have
the current working folder on a flash drive and not be connected to the
network, so that there is no path back to previous versions of the folder.
The problem can be exacerbated since the eight files from the contractors,
all need to be updated by those contractors and sent back to me. Our main
contractor also runs a folder to keep their own file and that of the
contractor's own contractor files which they update and send through.
Any thoughts would be most usefull and helpful, especially given I have
another simillar project due to start in the next three or four months and
would like not to have another two years of this again.
Regards
DavidC
DavidC,
I think the real answer is that you need Project Server. It is made for
just your situation. You may be able to get by with stand alone versions
of Project but you will NOT be able to move files around as you are now
trying to do. As you are finding out, it messes with the inter-file link
structure and will probably lead to file corruption.
John
Project MVP
.
- Follow-Ups:
- Re: Master schedules
- From: DavidC
- Re: Master schedules
- Prev by Date: Re: How do I use my FTP network as the hub for groove 2007?
- Next by Date: Re: Average work percentage
- Previous by thread: Re: How do I use my FTP network as the hub for groove 2007?
- Next by thread: Re: Master schedules
- Index(es):
Relevant Pages
|