Re: how do i change the default to start-to-start?
Tech-Archive recommends: Fix windows errors by optimizing your registry
- From: "Rod Gill" <rod AT project-systems DOT co DOT nz>
- Date: Thu, 17 Jan 2008 12:27:02 +1300
Hi,
Generally 80%+ of all links are finish to start so Microsoft hasn't provided
a way of changing that default. You could write VBA code to help but I
suspect you are best just creating links by typing them in the predecessor
column. For a Start-start link from task 5 to 6 in the predecessors column
for task 6 type 5SS
--
Rod Gill
Project MVP
Project VBA Book, for details visit:
http://www.projectvbabook.com
NEW!! Web based VBA training course delivered by me. For details visit:
http://projectservertraining.com/learning/index.aspx
----------------------------------------------------------------------------------------------------
"Té" <Té@discussions.microsoft.com> wrote in message
news:E71AD196-DA8A-411B-AB00-D63EC99540B9@xxxxxxxxxxxxxxxx
I am trying to change the predecessor default from finish to start to start
to start.
.
Relevant Pages
- Re: Run-Time Error 438 Problem
... following VBA error is ... >this is the first form where VBA code is encountered and ... > Microsoft Access 10.0 Object Library ... > Microsoft Visual Basic for Applications Extensibility ... (microsoft.public.office.developer.vba) - Re: Entourage / Office 2007 / VBA
... I'll hazard a guess that even Microsoft is in some doubt yet. ... were expecting VBA to disappear from PC Word also, ... Research reveals so little usage of VBA on Mac that there is no business ... VBA code contained within a Word file will remain there, ... (microsoft.public.mac.office) - Re: Running a VBA ppt from 2003 in 2002??
... There's NO problem running 2003 vba in XP so the problem is with the XP ... "Ron Ehrlich" wrote: ... I then pasted the vba code into a text file and sent the text file ... This post is a suggestion for Microsoft, ... (microsoft.public.powerpoint) - Re: Running a VBA ppt from 2003 in 2002??
... If I remember right Office XP made installing VBA ... I then pasted the vba code into a text file and sent the text file ... This post is a suggestion for Microsoft, ... (microsoft.public.powerpoint) - Re: Why to use VBA?
... all I am saying is its time to start introducing new features in .net that will do the same thing VBA does and give the market time to accept it without dropping VBA as you said executives are conservative to change VBA! ... The fact is that VB.NET is sufficiently incompatible with the previous version of VB (VB6, from which VBA is derived) that for all practical purposes an upgrade wasn't possible, you had to rewrite the code more or less from scratch. ... The automated code converters provided by Microsoft were next to useless, and the fact that Microsoft went and changed lots of names of objects and properties meant that late-binding code wouldn't work without rewrite because it couldn't be automatically converted at all. ... Lots of people asked Microsoft what that reason was, with regard to that and dozens of other changes to the language. ... (microsoft.public.word.vba.general) |
|