Re: Project Summary calculation

Tech-Archive recommends: Fix windows errors by optimizing your registry



Sorry, fingers not fully talking to brain. The message should have
said:
"Is there a half hour difference...."

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"JulieS" <passport6847 at maine dot rr dot com> wrote in message
news:uw9ewheLIHA.5684@xxxxxxxxxxxxxxxxxxxxxxx
Hi Chilvers,

Try showing time as well as date. Is there a half your difference
somewhere on the completed task as compared to the Project Summary
task?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"Chilvers" <Chilvers@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:733F6A43-22B5-48AC-BD79-582573FA5DEF@xxxxxxxxxxxxxxxx
Hi Julie
My calendar options show 8 hours, 8:00-5:00 as does my calendar, so I
don't
see any problem there... any other suggestions?
Chilvers

"JulieS" wrote:

Hello Chilvers,

The .07 variance you are seeing is most likely a 1/2 hour difference
between the setting on you calendar and the definition of a "day"
duration set in the Calendar options. Check FAQ #5 at:
http://project.mvps.org/faqs.htm

and confirm that your settings are correct.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project


"Chilvers" <Chilvers@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:C7AFD033-C95F-4FEB-B07F-4282ABE34207@xxxxxxxxxxxxxxxx
I have a 57 day project and I marked the first task 100% complete.
It
is a
2-day task completed on 2 days. On the Tracking Table, why does
my
Project
Summary show Actual Duration 2.07 and Duration Remaining 54.93
rather
than
Actual Duration 2 and Duration Remaining 55







.



Relevant Pages

  • Re: Changing Estimate Durations
    ... project plan that you or your boss has already devised. ... Visit http://www.mvps.org/project/faqs.htm for the FAQs ... Steve House [Project MVP] ... You literally have to assign duration, start and end dates 1 task ...
    (microsoft.public.project)
  • Re: Project Summary calculation
    ... Visit http://project.mvps.org/ for the FAQs and additional information ... about Microsoft Project ... My calendar options show 8 hours, 8:00-5:00 as does my calendar, ... Summary show Actual Duration 2.07 and Duration Remaining 54.93 ...
    (microsoft.public.project)
  • Re: Project Summary calculation
    ... "JulieS" wrote: ... Visit http://project.mvps.org/ for the FAQs and additional information ... My calendar options show 8 hours, 8:00-5:00 as does my calendar, ... Summary show Actual Duration 2.07 and Duration Remaining 54.93 ...
    (microsoft.public.project)
  • Re: Duration calculation
    ... then changed to 7 days a week so that the duration would show the ... Remember that the base calendar for working times sets the default work ... Steve House [Project MVP] ... Visit http://www.mvps.org/project/faqs.htm for the FAQs ...