Re: Working Time Display
Tech-Archive recommends: Fix windows errors by optimizing your registry
- From: "Jan De Messemaeker" <jandemes at prom hyphen ade dot be>
- Date: Thu, 18 Oct 2007 12:59:32 +0200
Hi,
No problem.
Through Tools, Change Working time, New, create a new calendar having as
nonworking time the days/weeks you want to stand out.
Then through Format, Timescale, nonworking time, select that calendar to
show on the Gantt Chart
You can color it more agressively than silver there too, by the way
Hope this helps,
--
Jan De Messemaeker
Microsoft Project MVP
http://users.online.be/prom-ade
"Nafs" <Nafs@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:C0D9AF7E-539B-42B9-9E0A-3C00EFD03384@xxxxxxxxxxxxxxxx
Please help before I tear ALL of my hair out.
I am trying to create a project for an on site installation lasting 6
months.
For 2 weeks of the period, there is a shutdown which I want to highlight
on
the Gantt chart in the form of a colour or shape, whatever, anything so
that
these two weeks will immediately stand out when the project is pinned up
on a
site office wall!
There is work ongoing during the shutdown period so I can't just make it
non-working time. Is there any way I can highlight nondefault working time
to
make it stand out?
--
Frustrated Project Engineer!!!!
.
Relevant Pages
- Re: Changing Duration
... To accomplish this, you could use a project calendar that shows 7 days each ... Click Tools - Change Working Time ... as both the Project calendar and the Nonworking time calendar. ... (microsoft.public.project) - Re: Duration calculation
... To clarify -- changing the information under Tools> Options, Schedule ... For details on changing the working time in Project 2007, ... Modify the calendar through Tools> Change Working Time. ... View tab: Date format showing date and time. ... (microsoft.public.project) - Re: Duration calculation
... a pain in Project 07 to do it under tools, change working time. ... Modify the calendar through Tools> Change Working Time. ... View tab: Date format showing date and time. ... Remember that duration is always measured in minutes and fractions ... (microsoft.public.project) - Re: Working Calendars
... I actually clicked on the default working time in the change working times ... calendar and changed that calendar to reflect 7:45 to 4:15 pm. So now when I ... Jackie Duncan ... did you also insure each resource uses that custom calendar? ... (microsoft.public.project) - Re: Duration Not Right When For a 24-hour Resource
... Duration time is only loosely related to time as indicated on the clock on the wall or tracked by conventional calendars such as your day-planner. ... In your example, because work is proceeding 24/7, the number of working time minutes between Monday 8am and Friday 12 noon IS the same as the number of working time minutes in 12.5 standard 8-hour workdays, thus in duration days the duration of that task is 12.5 days, not 4.25 even though the bar on the graphic only covers four days + out of the week. ... If the calendar governing that task is the standard 8-hour default ... (microsoft.public.project) |
|