Re: Scrolling synchronization
- From: JulieS <JulieS@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Wed, 3 Oct 2007 09:54:00 -0700
Hi Rick,
Hmmm. I just went to the connect site and after logging in with my Live ID
was able to add a suggestion. Do you have a Windows Live ID?
Julie
"Rick @ AnchorCM" wrote:
Thanks for the suggestion. Unfortunately, MS doesn't seem to have a way to.
join the discussion to make suggestions. I was referred to different sites
until I ended up back where I started. Looks like they have closed this
avenue for reporting problems.
I have a full log of MS project program failures. From 7/30 to 10/1 MS
Project has crashed 7 times--several after the scrolling synchronization has
stopped working.
Perhaps you can get this information to the project team since I can't.
"JulieS" wrote:
Hi Rick,
I am running Project 2007 here and have not personally experienced what
you report. A quick check of the connect site
(http://connect.microsoft.com/feedback/default.aspx?SiteID=235) didn't
return any similar problems. You may try logging the issue there to see
if other users have workarounds or other feedback.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
"Rick @ AnchorCM" <RickAnchorCM@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in
message news:438C7025-5ECE-4634-9B6E-01357ABF31C9@xxxxxxxxxxxxxxxx
I'm using Project 2007 w/ all recent updates on an IBM T60p. The
problem
manifests itself most often when using the mouse controls on the
computer
instead of an external mouse.
If I page up or down the data will realign but not resynchronize the
scrolling. The only way to reestablish the synchronization is to
restart
Project.
"JulieS" wrote:
Hi Rick,
What version of project are you using?
Does using the Go To Selected Task button restore order? You may
also
try CTRL+Home and the ALT+Home to reorient the left and right sides.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project
"Rick @ AnchorCM" <RickAnchorCM@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in
message news:4CE2E7B9-31A1-4850-BEDA-A9922B8FAFDD@xxxxxxxxxxxxxxxx
Occasionally, when scrolling the lefthand side of the Gantt window,
it
moves
independently from the RH side. As a result, the task descriptions
&
other
data don't align w/ the Gantt bars. The only fix I've found is to
close MPP
& restart. Any way to prevent this from happening?
- Follow-Ups:
- Re: Scrolling synchronization
- From: Rick @ AnchorCM
- Re: Scrolling synchronization
- From: Rick @ AnchorCM
- Re: Scrolling synchronization
- References:
- Re: Scrolling synchronization
- From: JulieS
- Re: Scrolling synchronization
- From: JulieS
- Re: Scrolling synchronization
- From: Rick @ AnchorCM
- Re: Scrolling synchronization
- Prev by Date: RE: Can I have a Multi-Line display in Project Gant view?
- Next by Date: Re: Filtering all subtasks tasks for a task
- Previous by thread: Re: Scrolling synchronization
- Next by thread: Re: Scrolling synchronization
- Index(es):