Re: staggered assignment for resources.

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



Hi,

1. See embedded
2. We do not have to look for a particular setting to make Leveling do that
but I think, rather to the particular set of settings you must have applied
to stop it from doing what you want

Since it's only a test file with a few tasks, let me stop the guesswork and
have a look instead.
You can send the file to

jandemesATprom-ade.be

Greetings,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"xlsstudent" <xlsstudent@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:88EB1CAD-47B2-49DB-9DFE-A3FE23224A7B@xxxxxxxxxxxxxxxx
Jan,

Thank you. But if RL was the soln, I would have solved it by now. This is
what happens when I try to level them. Say task1 is from 1/1 to 1/3. Task
2
is from 1/2 to 1/5. When you try to vele it, MS says it cannot level as it
has conflict.

??? What have you done to make it say that? Not normal, it can if you do not
make certain combinations of settings

I tried assigning priorities but it doesnot help with levelling either.

Indeed

This is what I want to accomplish. BA-Prepare for discovery meetings. Say
40
hrs. Start on 1/1 and go on. In between I may have to schedule client
meeting
for 8 hrs say on 1/4. If I create a task with constraint on 1/4, then
task 1
should automatically realise and fix the end date as 1/8 (1/6, 1,7 being
weekends). Is this something I can accomplish in MSP? If so how?

Whatever your experience, sorry, leveling does that if you allow it to
split tasks


Thanks for your response. Look forward for your valuable help.


"Jan De Messemaeker" wrote:

Hi,

Resource Leveling answers both questions.
Look up the help; it's a bit too large to explain here.
Greetings,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"xlsstudent" <xlsstudent@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:1E6D7C4D-16E4-41AF-9018-8F703D2112AF@xxxxxxxxxxxxxxxx
hi,

I am managing a complex program and need help in resource allocation.

My Business analyst works on BA activities let us say for 3 days and
hands
over to my tech architect. My tech architect may need about 10 days
while
my
BA starts working on next package. There has to be a meeting between
the
architect, BA and clients once my arhcitect is ready. my challenge is,
how
do
I allocate the BA in split form? If I say my BA will work on package1
from
day1 to day 3 and on package 2 from day 4 to day20. If the meeting with
client happens on day 18, then my BA will be 200% loaded which is
impractical. So need help to address this.

Also, is there a way, where project assigns resources only for 8hrs,
and
if
the resource already has 8hrs of work with higher priority will
automatically
assign the work to next day?






.



Relevant Pages

  • RE: In Project 2003 (SP1) I get unexpected leveling results
    ... I tried doing so in the Resource Usage View by typing in the hours for the ... Still not sure why Project causes gaps when leveling. ... based on the settings for these two as well as combinations of settings ...
    (microsoft.public.project)
  • Re: So many questions...so little time...on scheduling and leveling
    ... synchronous after leveling. ... give the resource a max. units of 100+x% ... has no other assignments on that day? ... What does it mean to assign a resource to a summary task while leaving ...
    (microsoft.public.project)
  • Re: So many questions...so little time...on scheduling and leveling and more
    ... What you ask for IS resource leveling, ... > schedule time that is different from the currently scheduled time. ... > I also envision a mode such that if two assignments overlap in time ...
    (microsoft.public.project)
  • Re: Accept or reject levelling
    ... Microsoft Project levels ALL resource overallocations on all ... only those whom you select before leveling. ... clear leveling in a task View, such as the Leveling Gantt view. ...
    (microsoft.public.project)
  • Re: Multiple source on single task
    ... I'm glad you're working your way through resource leveling. ... overallocation, it's for one of the following reasons: ... Ok, I'm on that window. ...
    (microsoft.public.project)