Re: staggered assignment for resources.

Tech-Archive recommends: Fix windows errors by optimizing your registry



Jan,

Thank you. But if RL was the soln, I would have solved it by now. This is
what happens when I try to level them. Say task1 is from 1/1 to 1/3. Task 2
is from 1/2 to 1/5. When you try to vele it, MS says it cannot level as it
has conflict.

I tried assigning priorities but it doesnot help with levelling either.

This is what I want to accomplish. BA-Prepare for discovery meetings. Say 40
hrs. Start on 1/1 and go on. In between I may have to schedule client meeting
for 8 hrs say on 1/4. If I create a task with constraint on 1/4, then task 1
should automatically realise and fix the end date as 1/8 (1/6, 1,7 being
weekends). Is this something I can accomplish in MSP? If so how?

Thanks for your response. Look forward for your valuable help.


"Jan De Messemaeker" wrote:

Hi,

Resource Leveling answers both questions.
Look up the help; it's a bit too large to explain here.
Greetings,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"xlsstudent" <xlsstudent@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:1E6D7C4D-16E4-41AF-9018-8F703D2112AF@xxxxxxxxxxxxxxxx
hi,

I am managing a complex program and need help in resource allocation.

My Business analyst works on BA activities let us say for 3 days and hands
over to my tech architect. My tech architect may need about 10 days while
my
BA starts working on next package. There has to be a meeting between the
architect, BA and clients once my arhcitect is ready. my challenge is, how
do
I allocate the BA in split form? If I say my BA will work on package1 from
day1 to day 3 and on package 2 from day 4 to day20. If the meeting with
client happens on day 18, then my BA will be 200% loaded which is
impractical. So need help to address this.

Also, is there a way, where project assigns resources only for 8hrs, and
if
the resource already has 8hrs of work with higher priority will
automatically
assign the work to next day?




.



Relevant Pages

  • Re: Resource reservation problem
    ... Are you sure the client is using the "Make a Meeting" to send the request? ... double-clicking ON IT trying to create a meeting directly on the resource. ...
    (microsoft.public.outlook.calendaring)
  • Re: staggered assignment for resources.
    ... What you want is normal Project behaviour. ... In between I may have to schedule client ... I am managing a complex program and need help in resource allocation. ... My tech architect may need about 10 days ...
    (microsoft.public.project)
  • Re: Leveling resources, spliting tasks but without change duration
    ... If I have a Task A with a resource allocated 10% and a task B with him also ... A & B needs to stop completely for the time he is in the meeting. ... place while his allocation for the meeting is going to be 100%. ... > the project says, correctilly, that there is no overallocation. ...
    (microsoft.public.project)
  • Re: Public Calendars as Resources - Attachments are Public?
    ... I'm not sure why setting the meeting to private didn't work, but then I'm a server guy. ... but there are lots of reasons it was removed in Exchange 2007/Outlook 2007 and lots of reasons that both Microsoft and others built products to replace it on Exchange 2003. ... on the resource mailbox. ... > attachments to these meetings are only visible to the attendees. ...
    (microsoft.public.exchange.admin)
  • Re: True Consulting Cost/Benefit
    ... Thanks for your suggestions and the question was not to be used for billing ... In fact most of our client projects where we will be ... salaries and have it factored into the cost of the projects for internal use ... While you can always record a billing rate for a resource, ...
    (microsoft.public.project)