Re: Interesting Date problem



Not sure on the formula, as this came from another person - any idea where
that formula would be located at?

"JulieS" <passport6847 at maine dot rr dot com> wrote in message
news:%23FWSvuV7HHA.980@xxxxxxxxxxxxxxxxxxxxxxx
Hello Charles,

Thanks for the additional information. The field titled "Projected or
Actual Start Date" appears to be a custom field with a formula. Could you
please give some details about:
(a) what is the field name that has been customized? (i.e. Text1, Date1)
(b) please copy and paste the formula in the field into your reply.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"Charles" <dylaninaz@xxxxxxxxx> wrote in message
news:%238mmar%236HHA.2380@xxxxxxxxxxxxxxxxxxxxxxx
Here's a little more clarification:

The error is occurring in the "Projected or Actual Start Date" column -
on
the orginal workstation, where for each entry that date has been
modified,
those dates show OK. On any other machine that you open it up to, the
"Projected or Actual Start Date" column defaults back to the
Project>Project
Information, Start Date field (which in this case is a default of
01/01/02).

So, I'm not thinking that it's corrupt - just in how those values had
gotten
changed, and now they somehow keep defaulting back.


"JulieS" <passport6847 at maine dot rr dot com> wrote in message
news:uj16dGb5HHA.4476@xxxxxxxxxxxxxxxxxxxxxxx
Thanks Charles. As it is occurring with just one project file, my
*guess* would be that there is some sort of mild corruption happening
with the file. I have had folks send me file that were acting oddly
only to have them open without incident on my machine.


If you'd like to send me the odd file, I'll take a look and see if I see
anything odd or unusual. I'd can't guarantee I'll find the answer, but
I'd be happy to take a look if you'd like.

My email address:
passport 6847 AT maine DOT rr DOT com.

remove spaces and replace AT with @ and DOT with periods.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"Charles" <dylaninaz@xxxxxxxxx> wrote in message
news:OriCHja5HHA.5724@xxxxxxxxxxxxxxxxxxxxxxx
Ms Project 2003 - 11.2.2005.1801.15 - SP2 - these are valid software
copies, currently occuring on just this one project file.

"JulieS" <passport6847 at maine dot rr dot com> wrote in message
news:%23Y$bXuZ5HHA.4476@xxxxxxxxxxxxxxxxxxxxxxx
Thanks for the update Charles. What versions of Project are
installed -- what service pack levels. Are all of the copies of the
software activated? Is this occurring on all project files or just
one?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"Charles" <dylaninaz@xxxxxxxxx> wrote in message
news:eDk9WhZ5HHA.4880@xxxxxxxxxxxxxxxxxxxxxxx
Checking the setting - it is currently set to Automatic.

"JulieS" <passport6847 at maine dot rr dot com> wrote in message
news:%235HX6cR5HHA.600@xxxxxxxxxxxxxxxxxxxxxxx
Hi Charles,

Assuming there are links (predecessors and successors in the project
file):

Check the "non-performing" computers -- is calculation set to
manual? See Tools > Options, Calculation tab. Enable (check)
automatic.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project


"Charles" <dylaninaz@xxxxxxxxx> wrote in message
news:e7CRZQQ5HHA.5724@xxxxxxxxxxxxxxxxxxxxxxx
I have a weird Project issue....

I have a Project plan that multiple users are using - it is not
published to a project server, has no leveling - it is a basic mpp
posted onto a share drive. When one user opens the project plan
file, all the dates are correct. When any other user opens it, they
all see incorrect dates, ie, most of the dates defaults to a
defualt start plan date. Anyone have any ideas what to check?

















.



Relevant Pages

  • Re: Interesting Date problem
    ... Project MVP ... Visit http://project.mvps.org/ for the FAQs and additional information ... information about Microsoft Project ... user opens it, they all see incorrect dates, ie, most of the ...
    (microsoft.public.project)
  • Re: Automatically updating the Current Date
    ... Project MVP ... Visit http://project.mvps.org/ for the FAQs and additional information ... You should see two entries in the Project Explorer Window ... Microsoft Project Objects and you should see an icon that looks like ...
    (microsoft.public.project)
  • Re: Interesting Date problem
    ... Project MVP ... Visit http://project.mvps.org/ for the FAQs and additional information ... information about Microsoft Project ... When one user opens the project ...
    (microsoft.public.project)
  • Re: "Error 1303" when trying to upgrade to 2007
    ... Project MVP ... Visit http://project.mvps.org/ for the FAQs and additional information ... about Microsoft Project ... I'm glad to know that the install did finally ...
    (microsoft.public.project)
  • Re: Interesting Date problem
    ... Visit http://project.mvps.org/ for the FAQs and additional information ... information about Microsoft Project ... I have a Project plan that multiple users are using - it is not ... When one user opens the project plan ...
    (microsoft.public.project)