Nairy wrote:
I need to change the number in the duration but without changing the date in
the star and finish colomns, for a certain estimation in my plan, is that
possible???
No as the duration is the number of working days between the start and
end dates.
Why don't you:
- Save your plan
- Adjust the task durations as required
- See the effect on the plan
- Close the plan without saving it
Alternatively, if you have Project 2007, then you can use the undo
features to get back to your original plan.
.
Relevant Pages
- Re: help
... that "% Complete" refers to duration, not work performed and not the amount ... the date the schedule shows and your input percentage of the total duration ... clue how I, my company, or the customer have arrived at this point. ... hasn't been a valid plan all along), ... (microsoft.public.project) - Re: help
... that "% Complete" refers to duration, not work performed and not the amount ... the date the schedule shows and your input percentage of the total duration ... clue how I, my company, or the customer have arrived at this point. ... hasn't been a valid plan all along), ... (microsoft.public.project) - Re: Working with task durations of minutes
... Just tell me I'm responsible for updating the server, everything will be "go" for me to do it starting Tuesday afternoon, and then get out of my way and let me do my job. ... From a project managment perspective it's usually enough for the PM to say "Update Server with Module Package X, 5 hours duration, starting Tuesday 1pm" and leave it up to Joe how he organizaes the details. ... If I'm painting a room and the painter and his assistant will box up the computers in it, move the furniture out, remove fixtures from the wall, mix and apply the paint I'll just list it as one task "Paint the Room." ... On the plan there are about 250 tasks that need ... (microsoft.public.project) - Re: Recording Completion when actual work is <> budgeted
... Planned Total Duration is 10 days. ... You have either been "efficient" or your Duration, Hours and Cost estimates ... Resources but do not appear in the plan. ... When filling in the Tracking fields it is always better to put in the data ... (microsoft.public.project) - Re: Milestones add time to projects?
... I think the overwhelming temptation to use fixed dates stems from the sheer terror of showing the boss a tentative plan where all the Gantt bars don't align to his assigned objectives and having to explain why the plan he outlined for us or our sales rep promised the client us won't work. ... The duration of a summary is from the start of the earliest task to the finish of the latest task, If I have a summary containing only two subtasks, both of them milestones of zero duration, and use a MSO or MFO contraint to fix the subtasks to dates 2 weeks apart, the summary will show a duration of 2 weeks. ... are somehow adding time to each sub-project. ... (microsoft.public.project) |
|