Re: Cost Vs. Sell Resource Rates

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance




Dear John;
Many thanks for your great help.
I did exacly what you wrote on the previous msg.
"
Sure. One simple way is to create a filter for either usage view.
Filter
on the Assignment field. Then select the first assignment, change the
cost rate table and do a fill down.
"
But i couldnt manage it. When i choose "B" then type crtl+D it doesnt
turn to "B".
I mean that i couldnt turn all items on the "cost rate table"colomn on
"task usage" window at the same time.

Thanks in advance for your kind help.

Regards


--
engineer12345
------------------------------------------------------------------------
engineer12345's Profile: http://forums.techarena.in/member.php?userid=30413
View this thread: http://forums.techarena.in/showthread.php?t=642863

http://forums.techarena.in

.



Relevant Pages

  • Re: Cost Vs. Sell Resource Rates
    ... One simple way is to create a filter for either usage view. ... on the Assignment field. ... cost rate table and do a fill down. ...
    (microsoft.public.project)
  • Re: Summary of Costs based on Cost Rate Tables applied
    ... text field and copy/paste the information from the Cost Rate Table ... In order to select the assignment ... Field Type: Task ... it doesnt filter to the sum of the As or Bs. ...
    (microsoft.public.project)
  • Re: Assignments Starting Before Today?
    ... although the Valuecolumn of the Filter Definition dialog box ... Using a spare Resource date field, I've used Now, Dateand ... the Assignment field. ... I'm a little unclear on what you've done with the spare date field. ...
    (microsoft.public.project)