Re: Cost Vs. Sell Resource Rates
- From: engineer12345 <engineer12345.2wagzi@xxxxxxxxxxxxx>
- Date: Sun, 2 Sep 2007 20:50:25 +0530
Dear John;
Many thanks for your great help.
I did exacly what you wrote on the previous msg.
"
Sure. One simple way is to create a filter for either usage view.
Filter
on the Assignment field. Then select the first assignment, change the
cost rate table and do a fill down.
"
But i couldnt manage it. When i choose "B" then type crtl+D it doesnt
turn to "B".
I mean that i couldnt turn all items on the "cost rate table"colomn on
"task usage" window at the same time.
Thanks in advance for your kind help.
Regards
--
engineer12345
------------------------------------------------------------------------
engineer12345's Profile: http://forums.techarena.in/member.php?userid=30413
View this thread: http://forums.techarena.in/showthread.php?t=642863
http://forums.techarena.in
.
- Follow-Ups:
- Re: Cost Vs. Sell Resource Rates
- From: Steve House
- Re: Cost Vs. Sell Resource Rates
- References:
- Re: Cost Vs. Sell Resource Rates
- From: engineer12345
- Re: Cost Vs. Sell Resource Rates
- Prev by Date: Prompt for Saving Baselines
- Next by Date: Re: How to Export Microsoft project to Excel?
- Previous by thread: Re: Cost Vs. Sell Resource Rates
- Next by thread: Re: Cost Vs. Sell Resource Rates
- Index(es):
Relevant Pages
|