RE: Bug? When I open my file, the tasks are renumbered and out of
- From: Kevin <Kevin@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Tue, 31 Jul 2007 13:42:01 -0700
Thank you for this link. It is most helpful. I think it is resolution #5,
regarding the blank lines. I have them, and I moved things around them. Maybe
I had one rolled up to a task by mistake. Either way, very large bug that
needs to be addressed in a patch by MS!
"Jim Aksel" wrote:
Sorry, I don't know if I can be of any more help because I have never had the.
problem.
Here is the link to the Microsoft Bug report on their feedback site:
https://connect.microsoft.com/feedback/ViewFeedback.aspx?FeedbackID=255404&SiteID=235
From there, people have posted 5 work arounds --- you can select "View" to
see them.
Hope that will help
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
"Kevin" wrote:
When I show the WBS, it shows up out of order (ex: 2.1, 1.1.6, 2.2), so if I
do a sort on that is messes up the order of the tasks again. There is only
one other person I have found online with this problem. He posted at
http://www.allpm.com/index.php?name=PNphpBB2&file=viewtopic&t=2136 but he did
not get a good reply. Maybe his explination is better than mine. I should
also point out, that while some IDs and information is still there, certain
items are missing their tasks names. The appear as rows with duration,
resources and predesessors, but no task name. Also, when I open the file I
get a circular reference message, but after I researched this, there wasn't a
circular reference to be found.
Do I have a corrupt file? Do I have a bad install?
"Jim Aksel" wrote:
Project/Sort/Sort By...
There is an option to permanently renumber the tasks in a check box at the
bottom.
Might I suggest examination of the WBS numbering since you may want to sort
by that to get you back to the original order.
Please keep a backup copy before making permanent file changes.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
"Kevin" wrote:
Thank you. This solves a portion of the problem, but causes another. Some of
the items were in the right order but got new IDs assigned to them, so the
sort took them our of order. For instance Items A, B and C were IDs 8, 9 and
10. Then when I opened the file, A, B and C were still in the right order on
the page, but numbered 9, 10, 8. So when I do the sort, it places C above A
and B.
"Jim Aksel" wrote:
This is a documented bug. Although your pain is felt by many, it is not felt
by all.
The work around is Project/Sort by ID.
Sorry for the inconvenience.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
"Kevin" wrote:
I'm using 2007, trying to work on a 2003 file. When I save I don't have any
issues. But when I reopen it, the IDs are out of order, my tasks are
renumbered and out of place. Some extra identation has occurred and some task
rows are hidden.
How do I get it back to normal?
- References:
- Prev by Date: Re: change legend titles
- Next by Date: RE: Exporting assignment information to Excel
- Previous by thread: RE: Bug? When I open my file, the tasks are renumbered and out of
- Next by thread: Re: Duration % S Curve
- Index(es):
Relevant Pages
|
Loading