Re: Constraints
- From: b10319 <b10319@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Thu, 26 Jul 2007 09:30:06 -0700
Ahhhh, that is definitely at least part of the problem because I am using the
"Standard" calendar and I have it set from 8:00am - 5:00pm. I'll try playing
around with that.
Thanks so much for your help!
"JulieS" wrote:
Hello Brian,.
MS Project can only schedule your tasks during working time as defined
in the project calendar. Unless you have modified either the standard
calendar or are using a modified calendar as the project calendar, the
working hours are 08:00 to 5:00 pm. In the scenario you describe I
assume the "5:00 pm ending task" is set as the predecessor in a finish
to start relationship with the "5:00 pm begin task". The problem is
that the working time ends at 5:00 pm so the next working time is 8:00
am the next day.
You'll need to either change the project calendar (Tool > Change Working
time) or if there are only some tasks which can carry on after 5:00 pm
you'll need to create a new calendar and assign the calendar as a task
calendar.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
"b10319" <b10319@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:3203ED39-9F4E-4A39-8C69-EF0B289FB658@xxxxxxxxxxxxxxxx
As a matter of fact, I do have a question. I was trying to set up my
schedule
as I described but I am running into a little snag that I don't know
how to
get around. All the "durations" are in "days" but I have a task that
needs
to ENDat 5:00 pm that needs to be a predecessor to a task that needs
to BEGIN
at 5:00 pm. I can't figure out how to get MSP to let me do that.
Instead,
it is throwing the subsequent task into the next day.
Thanks for your help,
Brian
"JulieS" wrote:
Hello b10319,
Well, for a self-described "newbie" you have already learned one of
the
best lessons -- yes, you do want to avoid using constraints as much
as
possible and build a dynamic schedule using predecessors and
successors.
Do you have a question or did you just want confirmation of your
understanding? :-)
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project
"b10319" <b10319@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:ED9F6BF6-74AC-4A40-B5B7-5687AEE5FA7A@xxxxxxxxxxxxxxxx
I am a newbie to MSP and am struggling with building my first
schedule.
For
starters, don't I want to avoid using constraints as much as
possible
and
build my schedule just using predecessors? That way, if I change a
start
date for example, all the dates throughout my project will adjust
in a
ripple
effect based on the durations I have indicated and I will end up
with
a new
completion date?
- Follow-Ups:
- Re: Constraints
- From: JulieS
- Re: Constraints
- References:
- Re: Constraints
- From: JulieS
- Re: Constraints
- From: JulieS
- Re: Constraints
- Prev by Date: Re: How to just get a SOLID BAR in Project, no Patterns offer it.
- Next by Date: RE: Simple SPI
- Previous by thread: Re: Constraints
- Next by thread: Re: Constraints
- Index(es):
Relevant Pages
|