Re: Constraints



Ahhhh, that is definitely at least part of the problem because I am using the
"Standard" calendar and I have it set from 8:00am - 5:00pm. I'll try playing
around with that.

Thanks so much for your help!

"JulieS" wrote:

Hello Brian,

MS Project can only schedule your tasks during working time as defined
in the project calendar. Unless you have modified either the standard
calendar or are using a modified calendar as the project calendar, the
working hours are 08:00 to 5:00 pm. In the scenario you describe I
assume the "5:00 pm ending task" is set as the predecessor in a finish
to start relationship with the "5:00 pm begin task". The problem is
that the working time ends at 5:00 pm so the next working time is 8:00
am the next day.

You'll need to either change the project calendar (Tool > Change Working
time) or if there are only some tasks which can carry on after 5:00 pm
you'll need to create a new calendar and assign the calendar as a task
calendar.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"b10319" <b10319@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:3203ED39-9F4E-4A39-8C69-EF0B289FB658@xxxxxxxxxxxxxxxx
As a matter of fact, I do have a question. I was trying to set up my
schedule
as I described but I am running into a little snag that I don't know
how to
get around. All the "durations" are in "days" but I have a task that
needs
to ENDat 5:00 pm that needs to be a predecessor to a task that needs
to BEGIN
at 5:00 pm. I can't figure out how to get MSP to let me do that.
Instead,
it is throwing the subsequent task into the next day.

Thanks for your help,

Brian

"JulieS" wrote:

Hello b10319,

Well, for a self-described "newbie" you have already learned one of
the
best lessons -- yes, you do want to avoid using constraints as much
as
possible and build a dynamic schedule using predecessors and
successors.

Do you have a question or did you just want confirmation of your
understanding? :-)

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project


"b10319" <b10319@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:ED9F6BF6-74AC-4A40-B5B7-5687AEE5FA7A@xxxxxxxxxxxxxxxx
I am a newbie to MSP and am struggling with building my first
schedule.
For
starters, don't I want to avoid using constraints as much as
possible
and
build my schedule just using predecessors? That way, if I change a
start
date for example, all the dates throughout my project will adjust
in a
ripple
effect based on the durations I have indicated and I will end up
with
a new
completion date?






.



Relevant Pages

  • Re: Outlook and dates
    ... If a task positively can only take place on the first of the month, create a calendar that shows the first of each month as the only working day and assign that calendar as the task calendar for the task of interest. ... Then the only days it will be scheduled on will be the first of the month - if its predecessor finishes the 15th of August, that task will be scheduled the 1st of September. ... If the contract requires you to ship on the 1st of September, it's up to you to arrange the predecessors and schdule their resources so its possible to ship on schedule - merely fixing the ship date to September 1 won't make it happen. ...
    (microsoft.public.project)
  • Re: Duration calculation
    ... To clarify -- changing the information under Tools> Options, Schedule ... For details on changing the working time in Project 2007, ... Modify the calendar through Tools> Change Working Time. ... View tab: Date format showing date and time. ...
    (microsoft.public.project)
  • Re: Problems with lead time on seperate computer
    ... However using EH as your basic unit of scheduling ignores resource availability, the differences between working time and non-working time through the day, etc. ... The number of days on the planner calendar on the wall that it takes him to do that depends on the number of hours a day that he is physically present and able to work. ... His working time calendar is crucial to the schedule - the elapsed time - number of sunrises and sunsets between when he starts and when he ends - is totally irrelevant to how long it will take him to do it. ... show durations in days while the other is set to show durations in hours. ...
    (microsoft.public.project)
  • Re: Start Finish dates
    ... Then I've created a simple schedule consisting of 10 ... in my calendar have I indicated a daily start time of 8:30. ... If your workday is 8 to 5 and your predecessor ends ... the successor will start Monday. ...
    (microsoft.public.project)
  • Re: How to schedule a whole day task?
    ... Create a new calendar where the only working time in the calendar is ... Conference' is a classic example project and most conferences ...
    (microsoft.public.project)