Re: General Task Question Please Help



That one was a gift, Mike.

Keith, everyone's been there. When it stings you, you never forget them. You
will be amazed at how many things seem un-intuitive at first but then seem
very natural.

Trevor RabeyTrevor Rabey 0407213955 61 8 92729485 PERFECT PROJECT PLANNING
www.perfectproject.com.au
"Mike Glen" <glenATmvps.org> wrote in message
news:OmGrTPuyHHA.748@xxxxxxxxxxxxxxxxxxxxxxx
Hi Keith,

It is!!

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials



"Keith Chadwick" <KeithChadwick@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in
message news:F28D0928-02B6-438B-9621-F1C3DA81B891@xxxxxxxxxxxxxxxx
. Very counter intuitive and should be available through
the right click menu on the Ghantt Chart itself.

I will have a look at mikes tutorials though.

Cheers
Keith

"JulieS" wrote:

Hello Keith,

I think some of the frustration you may be having is some difference in
terminology that Project uses versus how you are using it. I assume you
are saying the following:
1 task which you will allow 2 resources 1 week to complete. The total
amount of work (effort) for the resources is 8 hours and you want each
resource to perform half of the work -- or 4 hours each.

So, to Project:
1 task with a *duration* of 1 week
2 resources each assigned at 10% assignment units to allow them to
spread his/her 4 hours of work out over the one week. Total *work* 8
hours.

I suggest taking a read through fellow MVP Mike Glen's excellent series
of "how-to" articles on MS Project at:

http://project.mvps.org/mike's_tutorials.htm

I think you'll find them a terrific resource for getting you up and
running in the correct way with Project. The time you invest in some
upfront reading will pay off :-)

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project

"Keith Chadwick" <KeithChadwick@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in
message news:6B08C978-7557-4973-86AA-998784ABC61A@xxxxxxxxxxxxxxxx
I have been asked to set up the project schedule for an upcomming
project and
I am running into some frustration.

Simply put I have a task that will take 8 hours between 2 resources,
so 50%
allocated to each. But the task will be completed over a week. How
do I
show this is one task. Do I use the Lag feature? Or sub tasks one
for each
developer?

I have searched through the help and this basic information is not
provided.
Any help would be appreciated.

Cheers
Keith







.



Relevant Pages

  • Re: General Task Question Please Help
    ... MS Project MVP ... See http://tinyurl.com/2xbhc for Project Tutorials ... task which you will allow 2 resources 1 week to complete. ... I suggest taking a read through fellow MVP Mike Glen's excellent series ...
    (microsoft.public.project)
  • Re: Will the quitstart toolbar takes up the resources too?
    ... > Thank you, Mike. ... > Will the quitstart toolbar takes up the resources too? ... > Unless you install programs to the desktop, program icons are just ... > and has to have resources allocated to ALWAYS keep it there.. ...
    (microsoft.public.windowsxp.general)
  • Re: Swapping Resources ?
    ... Sure that makes sense but if Mike is replaced by Jim and both Mike and Jim ... Resources dialog box. ... After replacing Jim with Mike, shouldn't Jim's name no longer be ...
    (microsoft.public.project)
  • Re: How to force project not to split a task over multiple days
    ... Thanks Mike. ... You're simpler suggestion of taking the workshop off the plan will not work ... on all the other constraints and assignments. ... >> day and multiple resources assigned. ...
    (microsoft.public.project)
  • Re: beginner: difficulties with timeline
    ... Again there are some tasks that include multiple resources at the same time ... The meeting goes for an hour (Mike: this would be for example Task 11). ... in my understanding Project should ...
    (microsoft.public.project)