Re: General Task Question Please Help
- From: "Mike Glen" <glenATmvps.org>
- Date: Fri, 20 Jul 2007 16:37:29 +0100
Hi Keith,
It is!!
Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
"Keith Chadwick" <KeithChadwick@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:F28D0928-02B6-438B-9621-F1C3DA81B891@xxxxxxxxxxxxxxxx
. Very counter intuitive and should be available through
the right click menu on the Ghantt Chart itself.
I will have a look at mikes tutorials though.
Cheers
Keith
"JulieS" wrote:
Hello Keith,
I think some of the frustration you may be having is some difference in
terminology that Project uses versus how you are using it. I assume you
are saying the following:
1 task which you will allow 2 resources 1 week to complete. The total
amount of work (effort) for the resources is 8 hours and you want each
resource to perform half of the work -- or 4 hours each.
So, to Project:
1 task with a *duration* of 1 week
2 resources each assigned at 10% assignment units to allow them to
spread his/her 4 hours of work out over the one week. Total *work* 8
hours.
I suggest taking a read through fellow MVP Mike Glen's excellent series
of "how-to" articles on MS Project at:
http://project.mvps.org/mike's_tutorials.htm
I think you'll find them a terrific resource for getting you up and
running in the correct way with Project. The time you invest in some
upfront reading will pay off :-)
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
"Keith Chadwick" <KeithChadwick@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in
message news:6B08C978-7557-4973-86AA-998784ABC61A@xxxxxxxxxxxxxxxx
I have been asked to set up the project schedule for an upcomming
project and
I am running into some frustration.
Simply put I have a task that will take 8 hours between 2 resources,
so 50%
allocated to each. But the task will be completed over a week. How
do I
show this is one task. Do I use the Lag feature? Or sub tasks one
for each
developer?
I have searched through the help and this basic information is not
provided.
Any help would be appreciated.
Cheers
Keith
.
- Follow-Ups:
- Re: General Task Question Please Help
- From: Trevor Rabey
- Re: General Task Question Please Help
- References:
- Re: General Task Question Please Help
- From: JulieS
- Re: General Task Question Please Help
- From: Keith Chadwick
- Re: General Task Question Please Help
- Prev by Date: Re: I need a little bit of creativity
- Next by Date: Re: Project Portfolio Server 2006
- Previous by thread: Re: General Task Question Please Help
- Next by thread: Re: General Task Question Please Help
- Index(es):
Relevant Pages
|
Loading