Re: Duration calculation



What time does the task start on 7/21? What time does it end on 8/25? (Go to the Tools/Options menu, the View tab, and select a date format that displays the time as well as the date).

Remember that duration is always measured in minutes and fractions of a day at either end can make the real duration slightly off from the number you get counting dates on a calendar. For example, with a normal 8 hour workday with working time of 8am to 5pm, a task that begins at 1pm on Monday and finishes at noon on Wednesday has a 2 day duration, not 3 days as you might expect if you simply looked at the dates - starting Mon and ending Wed - and ignored the times. Each 8 hour interval is a day. Monday afternoon is 1/2 day, Tuesday is 1 full day, and Wednesday morning is the final half day, giving from Monday apparently through Wednesday a total duration of 2 8-hour days.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"trevor" <trevor@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message news:0E19AD7B-98DC-44FA-9171-7E99ED84E372@xxxxxxxxxxxxxxxx
I checked to see if there were any non-working days in the change working
time and there were not. Still confused about it.
trevor

"JulieS" wrote:

Hello Trevor,

Well obviously, I was not thinking straight or something. Either too
much coffee or not enough. When I create a task with a start date of
July 21, 2007 at 8:00 am and enter a 35 day duration, I show August 24,
2007 at 5:00 pm as the finish date. A duration of 36 days gives me
August 25, 2007. Is it possible you have one nonworking day in between
those dates?

Sorry for any ealier confusion.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"JulieS" <passport6847 at maine dot rr dot com> wrote in message
news:e1LNHxZxHHA.4076@xxxxxxxxxxxxxxxxxxxxxxx
> Hello Trevor,
>
> You have obviously modified the project calendar to allow every day
> (Sunday through Saturday) as working time. What hours (8:00 am to
> 5:00 pm ?) do you have set? If you haven't modified the 8:00 am to
> 5:00 pm and haven't modified the definition of the number of hours in
> a day from default (8 hours) then from July 21, 2007 8:00 am to August
> 25, 2007 5:00 pm *is* 35 eight hour time slots, thus 35 "days" not 36.
>
> See FAQ #5 at http://project.mvps.org/faqs.htm for some additional
> information.
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional information
> about Microsoft Project
>
>
> "trevor" <trevor@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> news:E0983075-0299-4A81-BBA8-296889C43208@xxxxxxxxxxxxxxxx
>>I have a schedule that spans from 7/21 to 8/25. Project is telling me
>>the
>> duration is 35 days, but when I count the days on the calandar, its
>> 36 days.
>> I need the proper count to show.Thanks.
>
>




.



Relevant Pages

  • Re: DAY versus HR assignation dilemna
    ... MS Project MVP ... See http://tinyurl.com/2xbhc for my free Project Tutorials ... if future Microsoft Project questions come up. ... > Be awae that Project distinguishes Duration from Work. ...
    (microsoft.public.project)
  • Re: Strange feature
    ... Visit http://project.mvps.org/ for the FAQs and additional information ... does appear with fixed duration and fixed units. ... information about Microsoft Project ... I discovered a strange feature in Project Pro 2007: ...
    (microsoft.public.project)
  • Re: "e days" estimated or elapsed duration does not show up in sum
    ... MS Project MVP ... StaciW wrote: ... duration event or does it simply show the duration regardless of how ... Microsoft Project Most Valuable Professional ...
    (microsoft.public.project)
  • Re: "e days" estimated or elapsed duration does not show up in sum
    ... FAQs, companion products and other useful Project information can be seen at ... duration event or does it simply show the duration regardless of how ... Microsoft Project Most Valuable Professional ... Are summary tasks 'capable' of displaying estimated duration tasks ...
    (microsoft.public.project)
  • Re: Task Not Marked AS Completed
    ... Visit http://www.mvps.org/project/faqs.htm for the FAQs ... resources declare remaining work 0 the duration becomes 2 days. ... Jan De Messemaeker, ... Microsoft Project Most Valuable Professional ...
    (microsoft.public.project)

Loading