Re: Duration calculation
- From: "JulieS" <passport6847 at maine dot rr dot com>
- Date: Sat, 14 Jul 2007 01:20:06 -0400
Hello Trevor,
Well obviously, I was not thinking straight or something. Either too
much coffee or not enough. When I create a task with a start date of
July 21, 2007 at 8:00 am and enter a 35 day duration, I show August 24,
2007 at 5:00 pm as the finish date. A duration of 36 days gives me
August 25, 2007. Is it possible you have one nonworking day in between
those dates?
Sorry for any ealier confusion.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
"JulieS" <passport6847 at maine dot rr dot com> wrote in message
news:e1LNHxZxHHA.4076@xxxxxxxxxxxxxxxxxxxxxxx
Hello Trevor,
You have obviously modified the project calendar to allow every day
(Sunday through Saturday) as working time. What hours (8:00 am to
5:00 pm ?) do you have set? If you haven't modified the 8:00 am to
5:00 pm and haven't modified the definition of the number of hours in
a day from default (8 hours) then from July 21, 2007 8:00 am to August
25, 2007 5:00 pm *is* 35 eight hour time slots, thus 35 "days" not 36.
See FAQ #5 at http://project.mvps.org/faqs.htm for some additional
information.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
"trevor" <trevor@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:E0983075-0299-4A81-BBA8-296889C43208@xxxxxxxxxxxxxxxx
I have a schedule that spans from 7/21 to 8/25. Project is telling me
the
duration is 35 days, but when I count the days on the calandar, its
36 days.
I need the proper count to show.Thanks.
.
- References:
- Re: Duration calculation
- From: JulieS
- Re: Duration calculation
- Prev by Date: Re: 24 Hour Schedule
- Next by Date: Re: Task Usage View and Work Decimal Digits
- Previous by thread: Re: Duration calculation
- Next by thread: Re: Duration calculation
- Index(es):
Relevant Pages
|