Re: Duration calculation



Hello Trevor,

You have obviously modified the project calendar to allow every day
(Sunday through Saturday) as working time. What hours (8:00 am to 5:00
pm ?) do you have set? If you haven't modified the 8:00 am to 5:00 pm
and haven't modified the definition of the number of hours in a day from
default (8 hours) then from July 21, 2007 8:00 am to August 25, 2007
5:00 pm *is* 35 eight hour time slots, thus 35 "days" not 36.

See FAQ #5 at http://project.mvps.org/faqs.htm for some additional
information.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"trevor" <trevor@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:E0983075-0299-4A81-BBA8-296889C43208@xxxxxxxxxxxxxxxx
I have a schedule that spans from 7/21 to 8/25. Project is telling me
the
duration is 35 days, but when I count the days on the calandar, its 36
days.
I need the proper count to show.Thanks.


.



Relevant Pages

  • Re: Project Duration
    ... So when you say a task has a duration of "1 month" Project has to convert that into the "real" duration units of hours for processing and storage. ... So for your example, if the "days per month" field (Calendar Options) is at the default 20 days, entering "12 months" for a task duration gets converted to 12*20=240 working days. ... That generic normal schedule is what your project calendar should reflect. ... Because task schedules normally follow the work schedule of the resources assigned to them, if I then put a swing shift worker on it, its hours will switch to swing shift as it should. ...
    (microsoft.public.project)
  • Re: Elapsed duration
    ... Duration in Project is always the span of time from the ... start date of the task to the finish date of the task in working time units ... the project calendar is the "Standard" ... 31 and have the Task and Subtask show a duration of 3 months? ...
    (microsoft.public.project)
  • RE: Summary Task Duration Adding to Fraction
    ... Has your project calendar been modified with non-working time? ... duration field. ... "Tina Winter" wrote: ... If I can't get rid of it, how can I format the duration ...
    (microsoft.public.project)
  • Re: Duration change when Assigniing resource pool.
    ... Remember Project uses minutes as the base unit for duration - days, etc are displayed only as a convenience to the user. ... I'm a big believer that the Project Calendar should NOT represent the overall hours of operation of the firm but instead they should be the normal working shift of a typical resource assigned to the project. ... and working days between the new projects and the resource pool. ...
    (microsoft.public.project)
  • Re: Duration Calculation
    ... The actual elapsed timed that transpires from when the task begins until it ends is calculated using the calendar that controls that task - the Project Calendar that for tasks that do not have resources assigned and the Resource task for the assigned resource for tasks that do. ... That is still a "1 day" task because the phrase "1 day duration" really means "how ever long it takes to have been on the job for 8 working hours" and that's what the duration in the Gantt chart will show. ...
    (microsoft.public.project)