Re: Trying to understand MSP 2003/2000 behavior
- From: David <davidd31415@xxxxxxxxxx>
- Date: Sun, 13 May 2007 22:02:57 -0400
In article <O20NZrUlHHA.1624@xxxxxxxxxxxxxxxxxxxx>, "Mike Glen"
<glenATmvps.org> says...
Hi David,Thanks for the welcome Mike. I hope to learn a bit here!
Welcome to this Microsoft Project newsgroup :)
Have you set Project/Project Information to show the Project Start Date as
1200am on 16 May? If not, I suspect it's starting at the default time of
0800 on the first day.
I checked the project start time, it is 1200am on 16 May. I believe it
is starting at 0800 on the first day because the resource is using a
standard calendar.
The two things I would really like to understand before anything else
are why the second task ends up splitting at the end in the strange way
it does and why the second task starts at 4pm on Monday and only has one
hour of work on that day.
Using different dates makes quite a difference too; using the same
weekday on other weeks produces different results (often being exactly
what I expect in the first place).
I would really appreciate some help with either of those questions (the
first two in my original post). As is right now I am hesitant to do
much of anything with Project because it seems after studying and
working with it for a few months I can not explain things that are
happening with only two tasks and one resource involved!!
Thanks again,
David
FAQs, companion products and other useful Project information can be seen at.
this web address: http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
"david" <davidd31415@xxxxxxxxxx> wrote in message
news:Xns992E87E1F761davidd31415yahoocom@xxxxxxxxxxxxxxxxx
I am trying to understand certain MSP behavior which I have seen with both
2000 and 2003.
The first thing I am trying to understand is why Project splits the end of
fixed duration tasks in strange ways. Here is what I have done:
Settings:
Work starts on: Sunday
Default start time: 12:00 AM
Default end time: 12:00 AM
Hours per day: 24.00
Hours per week: 168.00
Days per month: 30
24 hr project calendar
Resource #1
Standard calendar
No availability configured
Task #1
Start date: 5/16/07
Duration: 5 days
Work: 0
Constraint date: 5/16/07
Constraint type: Start no earlier than
Predecessor(s): none
Successor(s): none
Lag: none
- References:
- Trying to understand MSP 2003/2000 behavior
- From: david
- Re: Trying to understand MSP 2003/2000 behavior
- From: Mike Glen
- Trying to understand MSP 2003/2000 behavior
- Prev by Date: Re: special task property
- Next by Date: Re: Custom end-date field
- Previous by thread: Re: Trying to understand MSP 2003/2000 behavior
- Next by thread: Re: Trying to understand MSP 2003/2000 behavior
- Index(es):
Relevant Pages
|