Budget Baselines

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



Hello,

I would like to use a Baseline Budget field (for example Baseline 5
Budget Work), to enter manually in the Resource Usage page the amount
of hours requested fo that specific resource (in addition to the
normal usage of the Busget Work field) and I would like to view that
information in a Data Analysis view. I have already tried and if I do
not save the baseline of my selected field, the pivot table does not
include that amount. The problem is that if I save the baseline of my
selected field, I will loose all changes and info manually inserted.
Is there a workaround of your knowledge.
Thanks,
Claudia

.



Relevant Pages

  • Re: How do behavioral/anomaly detection systems learn?
    ... a baseline of network traffic and flag on behavior that widely varies ... checking for encrypted tunnels over port 80 by the amount of traffic ... offending hosts profile. ... conjunction with signature based systems. ...
    (Focus-IDS)
  • Re: Task bar old location
    ... Yes, the baseline shows where the task had been, but what were shooting for ... you don't know the amount of time it was extended. ... displayed the previous schedule overlayed by the current schedule. ... Maybe just the ability to overlay a complete schedule, ...
    (microsoft.public.project)
  • Re: Inscribing text within a circle
    ... readily available that will allow me to produce a small amount of text in ... graphical form where the baseline or the letter tops follow the radius of a ...
    (comp.os.linux)
  • Baseline Value Roll-ups no working
    ... resource usage view, to do the breakout, it won't sum up the Baseline Work or ... Baseline Cost values. ...
    (microsoft.public.project)
  • Re: Re: Duration and finish date
    ... In addition to Jan's comments, your planned duration, ... If you baseline the tasks or project before ... overtime field to the task or resource usage view as Jan ...
    (microsoft.public.project)