Re: Summary task does not pick up finish date of sub-tasks

Tech-Archive recommends: Fix windows errors by optimizing your registry



Hello Fiordispina,

Try pressing the F9 key on your keyboard to force a calculation. If the
date changes after pressing F9, it would appear that your calculation is
set to manual. Set it to automatic through Tools > Options, Calculation
tab.

Also, your comment "I changed all of the sub-task finish dates (and
removed all constraints of the sub-tasks)" is contradictory. If you
manually changed the finish dates, your tasks are still constrained :-).
Add the constraint type column to the table and ensure the tasks are all
set to ASAP -- assuming a project scheduled from a fixed start date.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"Fiordispina" <Fiordispina@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:BDA594F2-5596-4C32-AC2A-54A529F0E2A6@xxxxxxxxxxxxxxxx
I have a summary task that has multiple sub-tasks. I changed all of
the
sub-task finish dates (and removed all constraints of the sub-tasks)
and the
summary task continues to reflect the original finish date (two months
later
than new date).
There are no predecessors, no links, no constraints set.
Help please! Thank you.


.