Re: Percent complete



In article <6EC31A78-6D6D-47DF-B9F5-67F3472F86A7@xxxxxxxxxxxxx>,
atheil <atheil@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:

John--I would be happy to send you the file. How do I go about doing that?
Aimee

Aimee,
Just zip it and e-mail to the address I gave (not the address in my
header).
John

"John" wrote:

In article <67C7D60A-E96A-4178-9540-B7F1DE586653@xxxxxxxxxxxxx>,
atheil <atheil@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:

John,

I inserted the column %work complete--that for each sub-task related to
this
particular summary task is marked at 100%. For the summary task %work
complete, it has calculated 98% and for %complete, it has calculated 99%.
I'm
really confused now!

Thank you.

atheil,
Well, this can't be that difficult but I'm out of quick answers. Unless
someone else chimes in with a solution, I'd like to take a look at your
file. You can send it to me at the address below.

John
Project MVP
jensenj6atatcomcasttdotdotnet
(remove obvious redundancies)

"John" wrote:

In article <A000AD53-C0E0-42BF-A183-CCF60E3F674A@xxxxxxxxxxxxx>,
atheil <atheil@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:

Each task for the summary task is marked 100% complete. We are not
using
%
work complete.

atheil,
Well, just because you are not using a particular field doesn't mean it
is out of the picture. Do you have resources assigned to your tasks? If
so, then % Work Complete is relevant. Insert that field as a column and
see what value is listed for each subtask.

John
Project MVP

"John" wrote:

In article <D7E51747-579B-4D10-B9A9-B21A8AC25028@xxxxxxxxxxxxx>,
atheil <atheil@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:

I have 10 sub-tasks that are marked 100% each. The summary task
for
these
sub-tasks only show 99% complete. Why would this occur?

atheil,
Are there any milestones? If so, they also must be 100% complete.
How
about % Work Complete, is that also at 100% for all subtasks?

John
Project MVP



.



Relevant Pages

  • Re: Percent complete
    ... "John" wrote: ... atheil wrote: ... particular summary task is marked at 100%. ... Project MVP ...
    (microsoft.public.project)
  • Re: Percent complete
    ... atheil wrote: ... particular summary task is marked at 100%. ... Project MVP ... see what value is listed for each subtask. ...
    (microsoft.public.project)
  • Re: Summary Task set at 99% Complete
    ... Resource Sheet!!! ... As John says, a linked task, resources assigned to a summary task bar ... > updating them to 100% complete, the summary task updates to 99% complete. ... >> Project MVP ...
    (microsoft.public.project)
  • Re: Copy UserDefined Fields from Summary to subtask
    ... "John" wrote: ... i meant summary task and sub task. ... If you are trying to copy spare fields from the parent task to ... >>> Project MVP ...