Re: Percent complete
- From: John <mjensen@xxxxxxxxxxxx>
- Date: Mon, 19 Feb 2007 10:33:20 -0700
In article <6EC31A78-6D6D-47DF-B9F5-67F3472F86A7@xxxxxxxxxxxxx>,
atheil <atheil@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:
John--I would be happy to send you the file. How do I go about doing that?
Aimee
Aimee,
Just zip it and e-mail to the address I gave (not the address in my
header).
John
.
"John" wrote:
In article <67C7D60A-E96A-4178-9540-B7F1DE586653@xxxxxxxxxxxxx>,
atheil <atheil@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:
John,
I inserted the column %work complete--that for each sub-task related to
this
particular summary task is marked at 100%. For the summary task %work
complete, it has calculated 98% and for %complete, it has calculated 99%.
I'm
really confused now!
Thank you.
atheil,
Well, this can't be that difficult but I'm out of quick answers. Unless
someone else chimes in with a solution, I'd like to take a look at your
file. You can send it to me at the address below.
John
Project MVP
jensenj6atatcomcasttdotdotnet
(remove obvious redundancies)
"John" wrote:
In article <A000AD53-C0E0-42BF-A183-CCF60E3F674A@xxxxxxxxxxxxx>,
atheil <atheil@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:
Each task for the summary task is marked 100% complete. We are not
using
%
work complete.
atheil,
Well, just because you are not using a particular field doesn't mean it
is out of the picture. Do you have resources assigned to your tasks? If
so, then % Work Complete is relevant. Insert that field as a column and
see what value is listed for each subtask.
John
Project MVP
"John" wrote:
In article <D7E51747-579B-4D10-B9A9-B21A8AC25028@xxxxxxxxxxxxx>,
atheil <atheil@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:
I have 10 sub-tasks that are marked 100% each. The summary task
for
these
sub-tasks only show 99% complete. Why would this occur?
atheil,
Are there any milestones? If so, they also must be 100% complete.
How
about % Work Complete, is that also at 100% for all subtasks?
John
Project MVP
- References:
- Re: Percent complete
- From: John
- Re: Percent complete
- From: John
- Re: Percent complete
- From: John
- Re: Percent complete
- From: atheil
- Re: Percent complete
- Prev by Date: Autofilter within macros
- Next by Date: Re: Access a Flag from Task view in a Resource View
- Previous by thread: Re: Percent complete
- Next by thread: Re: Does anyone have a good redsidential builing template with cost b.
- Index(es):
Relevant Pages
|