Re: Base Calendar showing exceptions
- From: "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com>
- Date: Wed, 31 Jan 2007 13:30:23 -0700
Sandhya --
In the future, please post your Project Server questions to the
microsoft.public.project.server newsgroup, as this newsgroup is dedicated to
the Microsoft Project desktop application only. To modify enterprise
Calendars, you must do this from PWA. Navigate to the Server Settings page
in PWA and then click the Enterprise Calendars link in the Enterprise Data
section of the page. On that page, click the name of the calendar you wish
to edit. From there you can edit the calendar as you wish. Hope this
helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"
"Sandhya Gupta" <SandhyaGupta@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:897F29FC-4DAE-49D4-9869-FE8CD3B47000@xxxxxxxxxxxxxxxx
I am using project 2007 with project server.
I clicked on Change Working Time to see the Standard project Calendar.
There are few exceptions that are listed. All exceptions are "Unnamed". I
cannot delete the exceptions or view details of the exceptions.
Even though I am administrator and has permission to modify/create the
calendar, both "Create New Calendar" and "Add Calendar to Enterprise"
options
are disabled.
Any suggestions will be useful.
Thanks,
Sandhya
.
- Prev by Date: Re: Import outline level from Excel to Project
- Next by Date: Re: What format to publsih or republish in
- Previous by thread: Re: Base Calendar showing exceptions
- Next by thread: Re: Setting Gantt Date Range
- Index(es):
Relevant Pages
|