Re: Cost Vs. Sell Resource Rates



In article <tbeck.2ivlng@xxxxxxxxxxxxx>,
tbeck <tbeck.2ivlng@xxxxxxxxxxxxx> wrote:

Thanks John,
is there a way to toggle all of the rates from "A" to "B" throughout
the project or would I have to change them Per task line by line.

tbeck,
Sure. One simple way is to create a filter for either usage view. Filter
on the Assignment field. Then select the first assignment, change the
cost rate table and do a fill down.

John
.



Relevant Pages

  • Re: Cost Vs. Sell Resource Rates
    ... One simple way is to create a filter for either usage view. ... on the Assignment field. ... I mean that i couldnt turn all items on the "cost rate table"colomn on ...
    (microsoft.public.project)
  • Re: Assignments Starting Before Today?
    ... although the Valuecolumn of the Filter Definition dialog box ... Using a spare Resource date field, I've used Now, Dateand ... the Assignment field. ... I'm a little unclear on what you've done with the spare date field. ...
    (microsoft.public.project)
  • Re: Summary of Costs based on Cost Rate Tables applied
    ... text field and copy/paste the information from the Cost Rate Table ... In order to select the assignment ... Field Type: Task ... it doesnt filter to the sum of the As or Bs. ...
    (microsoft.public.project)