Re: Cost Vs. Sell Resource Rates
- From: John <mjensen@xxxxxxxxxxxx>
- Date: Fri, 15 Dec 2006 19:29:19 -0700
In article <tbeck.2ivlng@xxxxxxxxxxxxx>,
tbeck <tbeck.2ivlng@xxxxxxxxxxxxx> wrote:
Thanks John,
is there a way to toggle all of the rates from "A" to "B" throughout
the project or would I have to change them Per task line by line.
tbeck,
Sure. One simple way is to create a filter for either usage view. Filter
on the Assignment field. Then select the first assignment, change the
cost rate table and do a fill down.
John
.