Re: How to schedule a 'whole day' task?

Tech-Archive recommends: Fix windows errors by optimizing your registry



Hi Derek,

You're most welcome and thanks for the feedback. To your question of
"tricks", I'm afraid I don't know of one off the top of my head. The
work-around I posted has been posted on this site several times, but
trying to find it can be challenging .

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"DWD" <DWD@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:78D4CE47-52F5-48DB-A30C-1AB6950321F9@xxxxxxxxxxxxxxxx
Hi Julie

That does exactly what I want. Thanks very much. Is there a site which
collects tricks like this where I could search next time? I tried a
general
web search and searching this forum (with several different sets of
words)
but, obviously, didn't find this method.

Thanks again.

Derek.

"JulieS" wrote:

Hi DWD,

A work-around that has been used in the past that may work for you:

Create a new calendar where the only working time in the calendar is
for
one minute sometime after your default working time. (For example if
your working time is defined as 08:00 to 17:00, create the new
calendar
with 17:01 to 17:02 as working time.)

Assuming your "training" task has a predecessor - task A. Insert a
task
between Task A and your "training" task and ensure the link is A >
new
task > training task. Set the duration of the new task to one
minute.

Assign the new calendar to the new task. That task will always be
scheduled for 17:01 to 17:02 forcing the successor training task to
start the next working day at 08:00

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project


"DWD" <DWD@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:8D5BDA08-3FC5-4633-A205-2CD5F73DB80D@xxxxxxxxxxxxxxxx
I'm sure this must have been discussed before but Ican't figure out
how to do
this.

I'm working on a development project which includes as a 'task'
training the
users. This should will take a day and should, obviously, be
scheduled
as a
whole day, i.e. Project shouldn't break it down in 8 hours and
schedule it
for 2-5pm on Friday and 8-1pm on Monday!

How do I specify that a single day task should not span days or,
more
generally, that a task should align with day boundaries?

As I said, I'm sure this must have come up before since 'Scheduling
a
Conference' is a classic example project and most conferences
expect
to start
at 9am Day 1 and run to 5pm on Day X, rather than start and stop at
arbitrary
times.

Regards





.



Relevant Pages

  • Re: Duration calculation
    ... To clarify -- changing the information under Tools> Options, Schedule ... For details on changing the working time in Project 2007, ... Modify the calendar through Tools> Change Working Time. ... View tab: Date format showing date and time. ...
    (microsoft.public.project)
  • Re: Problems with lead time on seperate computer
    ... However using EH as your basic unit of scheduling ignores resource availability, the differences between working time and non-working time through the day, etc. ... The number of days on the planner calendar on the wall that it takes him to do that depends on the number of hours a day that he is physically present and able to work. ... His working time calendar is crucial to the schedule - the elapsed time - number of sunrises and sunsets between when he starts and when he ends - is totally irrelevant to how long it will take him to do it. ... show durations in days while the other is set to show durations in hours. ...
    (microsoft.public.project)
  • Re: How to schedule a whole day task?
    ... Create a new calendar where the only working time in the calendar is for ... one minute sometime after your default working time. ... Conference' is a classic example project and most conferences expect ...
    (microsoft.public.project)
  • Re: Constraints
    ... MS Project can only schedule your tasks during working time as defined ... in the project calendar. ... assume the "5:00 pm ending task" is set as the predecessor in a finish ...
    (microsoft.public.project)
  • Re: Problems with lead time on seperate computer
    ... the resource for task A is a 24 hour calendar. ... working time calendar is crucial to the schedule - the elapsed time - number ... show durations in days while the other is set to show durations in hours. ...
    (microsoft.public.project)