Re: Change working time without changing duration?



Hi,

Copy the duration column
Change the options
DON'T FORGET TO ALSO CHANGE WORKING TIME (Tools, options, change working
time)
Now paste the copied values into the duration column.
HTH
--
Jan De Messemaeker
Microsoft Project MVP
http://users.online.be/prom-ade
"Mike R." <MikeR@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:72DF203B-2514-4565-83A9-02C528B55009@xxxxxxxxxxxxxxxx
I have a 6000+ line Project schedule and now they tell me that they work 9
hours a day, not 8. Since they want to resource load this thing and do
EVMS,
I need to put the right number of hours in the schedule. If I use Options
and
change the hours per day to 9 and hours per week to 45, Project changes
all
the durations to a wierd number (1 day becomes "0.89 day").

Any way to change the hours per day and keep the original Durations?

Thanks,
Mike R.


.