Re: Durations incorrect



In article <62F9A613-8BFA-4147-9968-EE2EF04989C8@xxxxxxxxxxxxx>,
Steve C <SteveC@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:

Yes, he does realize he's setting constraints, but his purpose for entering
dates is strictly to have Project do a quick duration calculation, that's
all. He deletes the tasks afterwards and uses the program properly.

I will try your suggestions. Thanks.
--
Steve C

Steve,
OK, that approach does work and it sounds like he understands what he is
doing.

John


"John" wrote:

In article <D55BFC0B-F15B-439A-804C-E914C1E52BD8@xxxxxxxxxxxxx>,
Steve C <SteveC@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:

What would cause a duration in a brand new project to calculate
differently
for two different users?

A co-worker of mine likes to open a new project, enter a task, then
manually
enter a Start and Finish date just to see the duration between the two
dates.
He recently entered a Start date of 1/15/07 and a Finish date of
4/16/07.
His program calculates the duration as 65.81 days, while my program
calculates it as 66 days.

What might be causing this discrepancy? Thanks.

Steve,
First of all, does your do-worker realize that he is setting a
constraint on every task that he manually enters a start and/or finish
date? Manually entering dates for tasks is NOT the way to create a
schedule - it effectively defeats Project's scheduling engine.

Project calculates duration based on various settings. First, it depends
on the working time calendar. The standard default calendar has a first
shift of 8:00 am to 5:00 pm with a 1 hour break at noon. Second, the
number of hours in a day, week and month (used to calculate duration) is
set by Tools/Options/Calendar tab. And third, the default start and end
times for tasks (Tools/Options/Calendar tab) is also 8:00 am 5:00 pm. A
difference in any one of these between your installations of Project
will affect new project files that are created on either PC.

I would check all the above settings between your PC and your
co-worker's PC. One of them is probably different.

John
Project MVP

.



Relevant Pages

  • Re: Resource actual hours
    ... "Steve W." ... What I meant by "The four hours of scheduled work on the task ... >>> had a duration of four hours" is that since only one person was ... >>> resources to a task then the hours of work (they all have the Work ...
    (microsoft.public.project)
  • Re: How to update for a whole number of remaining days?
    ... You're welcome, Steve, I hope you've got it sorted now :-) ... See http://tinyurl.com/2xbhc for my free Project Tutorials ... extend the duration to show a finish date ahead of the status. ... The remainder 50% of the task is set to status date which is several ...
    (microsoft.public.project)
  • Re: Cannot show actuals past scheduled day end
    ... Hi Steve: What I am looking to do is exactly what the project does today. ... simple way to seed the total actuals not just the scheduled. ... Just don';t be surprised that it shows 10 minutes duration. ... What minutes of the day count as "working time ...
    (microsoft.public.project)
  • Re: Durations incorrect
    ... enter a Start and Finish date just to see the duration between the two dates. ... schedule - it effectively defeats Project's scheduling engine. ... Project calculates duration based on various settings. ... on the working time calendar. ...
    (microsoft.public.project)
  • Re: Task End Dates
    ... "Steve House" wrote: ... day task starting any later than the start of the workday finishes ... FAQs, companion products and other useful Project information can be seen ... duration, it has the task end at the same time as the next task ...
    (microsoft.public.project)