Re: Different Dates in Differernt Machines

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance



So both have been calculated? Try pressing F9 on both machines.

Mike Glen
Project MVP

Arjun M wrote:
Mike,
I have manual tab in there.
The other machine has automatic tab selected.The dates on my machine
are right.

So please advice
Arjun M
Mike Glen wrote:
Hi Arjun,

Is Calculation set to Automatic on both machines?
Tools/Options.../Calculation tab.

FAQs, companion products and other useful Project information can be
seen at this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

Arjun M wrote:
Friends,
A strange problem.
I have a project plan defined with dates and resources.But when the
same project plan is opened in a different machine dates are
changed.So same project plan with same version has different dates.

Please advice to fix this
Arjun M



.



Relevant Pages

  • Re: Different Dates in Differernt Machines
    ... Adding to John's post - You don't tell Project the schedule you think you can work ... ... But my colleague has automatic tab turned on. ... project plan have come after extensive work with the architects. ... Arjun M wrote: ...
    (microsoft.public.project)
  • Re: Different Dates in Differernt Machines
    ... I have manual tab in there. ... The other machine has automatic tab selected.The dates on my machine ... I have a project plan defined with dates and resources.But when the ... Please advice to fix this ...
    (microsoft.public.project)
  • Re: Different Dates in Differernt Machines
    ... Is Calculation set to Automatic on both machines? ... companion products and other useful Project information can be seen at ... Arjun M wrote: ... I have a project plan defined with dates and resources.But when the ...
    (microsoft.public.project)