Re: Dependencies and out of sequence scenario.



In article <0DA272BC-2999-437B-B771-21A63BC4370A@xxxxxxxxxxxxx>,
Manis <Manis@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:

John,
Sorry. Didn't mean to frustrate you. (By the way, I found the answer, I'm
explaining it at the end).
I'll try again.
1. Create 3 simple tasks. You will notice that they all begin on the same
day.
2. Make task2 dependent on Task1 and task3 dependent on task2. This will
make the tasks fall in sequence. (One after another).
3. If I mark task2 complete, shouldn't task3 start ASAP? Does this not
translate as the completion date of task1?

Answer: When you mark the task complete, the actual finish date is set to
the "finish" date. i.e if the finish date is in the future and you mark it
complete today, the actual finish date will show the future date and not
today's date! (I didn't know that.)

Some examples
Task1 - 1 day 10/19 - 10/19
Task2 - 1 day 10/20 - 10/20 - depends on Task1
Task3 - 1 day 10/23 - 10/23 - depends on Task2

If I mark Task2 complete on 10/19. The actual finish is still set to 10/20
and not 10/19. This ensures that Task3 starts on 10/23 and not 10/20. If I
change the actual finish on Task2 to 10/02, The duration is set to 0, Task3
starts on 10/02.
This puts Task3 before Task1! Screwing up the whole plan. I was not sure if
this was happening in my plan. It didn't look like it. So, I wanted to know
why it was not happening.

Bottom line - the default behaviour of actual finish date is what is desired
and marking tasks complete ahead of schedule does not impact the plan. (Not
unless you mess around with the actual finish date).

Please let me know if there's more to this.

Thanks guys!
Manis.

Manis,
I thought I mentioned in an earlier response that if task progress is
entered via a task's Actual Start and Actual Finish fields, then Project
will change the Start and Finish fields to agree with the actual dates.
Project is simply adjusting the estimated dates (i.e. the schedule) to
agree with reality (i.e. actual dates). However if progress is entered
via the % Complete or % Work Complete fields, then Project will make the
Actual Start and Actual Finish fields equal to the scheduled dates.
Project is simply saying that the plan dates were good and the task was
preformed "on schedule". However, maybe it was someone else's post where
I explained this.

At any rate, it is a little confusing when you say, "If I mark task 2
compete on 10/19". Is 10/19 the day you entered 100% in the % Complete
field or is 10/19 the actual date the task was completed? In the former,
the task's actual finish date will indeed be 10/20, while in the latter,
the task's actual finish date will of course be 10/19.

Why would you want to set the actual finish date of a task to a date
before the task's scheduled start date? Indeed that is "screwing up the
whole plan". It is OK to enter an actual finish date without entering a
actual start date but that finish date MUST be on or after the scheduled
start date, otherwise the task duration doesn't make any sense.

Hopefully you now have a better understanding of how the Start, Finish,
Actual Start and Actual Finish fields interact.

John
Project MVP

"Manis" wrote:

This is a problem that I'm having in my project.
The project plan was complete and we had all the dependencies set. Many of
them were start to finish. Now during the project, I'm finding that many of
the successor tasks are actually complete before the predecessor!
I understand that the dependencies were setup wrong. The users say that the
dependencies are actually resource dependent instead of task dependencies.
For eg:- if a task is being executed by an experienced resource, he has the
required knowledge and does not have to wait for the predecessor to be
complete. Valid argument. The problem is that the task has a generic
resource
against it. So, at the time of planning, I don't know what kind of
dependency
to set. I elected to use "start to finish". (Don't ask why.)
Question : If a successor is set as complete before the predecessor, what
happens to the dates?
if Task1, Task2 & Task3 are to be executed in that sequence and I mark
Task2
as complete before Task1, what happens to the plan for Task1 and Task3?
.



Relevant Pages

  • Re: Dependencies and out of sequence scenario.
    ... If I mark task2 complete, ... Screwing up the whole plan. ... and marking tasks complete ahead of schedule does not impact the plan. ... The project plan was complete and we had all the dependencies set. ...
    (microsoft.public.project)
  • Re: Dependencies and out of sequence scenario.
    ... When you mark the task complete, the actual finish date is set to ... Screwing up the whole plan. ... and marking tasks complete ahead of schedule does not impact the plan. ... The project plan was complete and we had all the dependencies set. ...
    (microsoft.public.project)
  • Re: Scheduling from fixed finish dates?
    ... Plan the project in the traditional way with FS ... dependencies then go to Project Menu/ Select project information/ set the ... "Schedule From" box to "Project Finish" ... "Tom G." wrote in message ...
    (microsoft.public.project)
  • Re: Proper Leveling Techniques - Rescheduling to start later
    ... Start and Finish are what your schedule calls ... Baseline Start and Finish are your original starting plan ... otherwise to force the tasks to end up on certain dates - leveling has ... I don't know why you're so adament againt using SNET constraints in any ...
    (microsoft.public.project)
  • Re: Finish Date Auto Update
    ... I work for a door company who gives out ... want in that field and then they are always on schedule. ... > The check boxes you're referring to don't have any effect on that behavior - ... But if it deviates from the scheduled plan they MUST manually ...
    (microsoft.public.project)