Re: Dependencies and out of sequence scenario.
- From: Manis <Manis@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Wed, 18 Oct 2006 07:44:02 -0700
John,
Just tried it with the 3 tasks. Calculation is automatic. I did not enter
either dates. Confirmed that the constraint type is "as soon as possible" for
all 3 tasks.
When I mark task2 as complete. Nothing happened. I went to
Tools/options/calculation tab and clicked on "calculate now". Still nothing.
(I'm testing this on Project 2007 Beta).
This behaviour is what I expected and actually helps me with the current
plan. But I'm wondering why the dates won't move and how to let project
optimize the utilization by itself.
I guess my question is .. What is that 1 day that we now have, considered
as? To me, it means that the project has come to a stop for that period. May
or maynot be a good thing.
Thanks!
"John" wrote:
In article <BA848446-F0D3-4B61-BA8C-69F05A003EFF@xxxxxxxxxxxxx>,.
Manis <Manis@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:
Sorry guys, that was a typo. All the dependencies are Finish to Start. That's
what I meant to say. (I am little bit confused by the earlier answers.)
My concern with this scenario is just one.
Eg:
Task1 - 1 day - 11/01 to 11/01
Task2 - 1 day - 11/02 to 11/02
Task3 - 1 day - 11/03 to 11/03.
They are in the correct sequence and that's their dependency.
If Task2 is complete on let's say, 10/25 and I mark it as complete. In what
situation would Task3 start on 11/02? Because now there's nothing happening
on 11/02.
For simplicity sake, let's assume just 3 tasks and 1 resource.
Would the Task3 dates change to 11/02? In my experiments, it didn't do that
automatically. If this does not happen, how can I make this happen? (not that
I would want to. just curious).
Thanks,
Manis.
Manis,
Yeah, I wondered if it was a typo but I think both Mike and I took you
literally.
OK, about your scenario. If task 2 is completed early, task 3 will still
show as starting on 11/3 (not 11/2) if one of two things are true -
either calculation is set to manual (Tools/Options/Calculation tab), or
there is a start-no-earlier-than constraint on task 3. This constraint
will automatically be set by Project if you manually entered task start
dates.
One more comment. You may or may not want task 3 to automatically move
back to 10/26 as a start date. It depends on how valid your links were
in the first place. Clearly the link between task 1 and 2 was not
necessary since task 2 finished ahead of task 1. However, it may still
be true that task 3 cannot start until task 1 is complete. In that case,
the link should be changed accordingly.
John
Project MVP
"Mike Glen" wrote:
Hi Manis,
Welcome to this Microsoft Project newsgroup :)
There should be no direct relationship between resources and dependencies.
The logic should be set irrespective of the resource requirements. Logic
dictates that you have to have the walls built before you put on the roof.
This is a Finish (of the walls)-to-Start (starting the roof) relationship
and is generally the norm for most projects. This is the way you should
build your project. If you are unsure of this, have a read of my Guide to
Network Analysis in Article 1 referenced below. When you have defined the
logic to your satisfaction, you can then begin to assign resources. Then
you can let Project sort out overallocations by levelling. Thus, I would
begin by changing all the precedence links to be Finish-to-Start.
You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #1, at this site: http://tinyurl.com/2xbhc or
this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AU
TH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)
FAQs, companion products and other useful Project information can be seen
at
this web address: <http://www.mvps.org/project/>
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
Manis wrote:
This is a problem that I'm having in my project.
The project plan was complete and we had all the dependencies set.
Many of them were start to finish. Now during the project, I'm
finding that many of the successor tasks are actually complete before
the predecessor!
I understand that the dependencies were setup wrong. The users say
that the dependencies are actually resource dependent instead of task
dependencies. For eg:- if a task is being executed by an experienced
resource, he has the required knowledge and does not have to wait for
the predecessor to be complete. Valid argument. The problem is that
the task has a generic resource against it. So, at the time of
planning, I don't know what kind of dependency to set. I elected to
use "start to finish". (Don't ask why.)
Question : If a successor is set as complete before the predecessor,
what happens to the dates?
if Task1, Task2 & Task3 are to be executed in that sequence and I
mark Task2 as complete before Task1, what happens to the plan for
Task1 and Task3?
- Follow-Ups:
- References:
- Re: Dependencies and out of sequence scenario.
- From: Mike Glen
- Re: Dependencies and out of sequence scenario.
- From: Manis
- Re: Dependencies and out of sequence scenario.
- From: John
- Re: Dependencies and out of sequence scenario.
- Prev by Date: Re: Crash while scrolling a project
- Next by Date: Re: track when duration exceeds set number of days and flag
- Previous by thread: Re: Dependencies and out of sequence scenario.
- Next by thread: Re: Dependencies and out of sequence scenario.
- Index(es):
Relevant Pages
|