Re: Dependencies and out of sequence scenario.
- From: Manis <Manis@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Tue, 17 Oct 2006 10:18:01 -0700
Sorry guys, that was a typo. All the dependencies are Finish to Start. That's
what I meant to say. (I am little bit confused by the earlier answers.)
My concern with this scenario is just one.
Eg:
Task1 - 1 day - 11/01 to 11/01
Task2 - 1 day - 11/02 to 11/02
Task3 - 1 day - 11/03 to 11/03.
They are in the correct sequence and that's their dependency.
If Task2 is complete on let's say, 10/25 and I mark it as complete. In what
situation would Task3 start on 11/02? Because now there's nothing happening
on 11/02.
For simplicity sake, let's assume just 3 tasks and 1 resource.
Would the Task3 dates change to 11/02? In my experiments, it didn't do that
automatically. If this does not happen, how can I make this happen? (not that
I would want to. just curious).
Thanks,
Manis.
"Mike Glen" wrote:
Hi Manis,.
Welcome to this Microsoft Project newsgroup :)
There should be no direct relationship between resources and dependencies.
The logic should be set irrespective of the resource requirements. Logic
dictates that you have to have the walls built before you put on the roof.
This is a Finish (of the walls)-to-Start (starting the roof) relationship
and is generally the norm for most projects. This is the way you should
build your project. If you are unsure of this, have a read of my Guide to
Network Analysis in Article 1 referenced below. When you have defined the
logic to your satisfaction, you can then begin to assign resources. Then
you can let Project sort out overallocations by levelling. Thus, I would
begin by changing all the precedence links to be Finish-to-Start.
You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #1, at this site: http://tinyurl.com/2xbhc or
this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)
FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
Manis wrote:
This is a problem that I'm having in my project.
The project plan was complete and we had all the dependencies set.
Many of them were start to finish. Now during the project, I'm
finding that many of the successor tasks are actually complete before
the predecessor!
I understand that the dependencies were setup wrong. The users say
that the dependencies are actually resource dependent instead of task
dependencies. For eg:- if a task is being executed by an experienced
resource, he has the required knowledge and does not have to wait for
the predecessor to be complete. Valid argument. The problem is that
the task has a generic resource against it. So, at the time of
planning, I don't know what kind of dependency to set. I elected to
use "start to finish". (Don't ask why.)
Question : If a successor is set as complete before the predecessor,
what happens to the dates?
if Task1, Task2 & Task3 are to be executed in that sequence and I
mark Task2 as complete before Task1, what happens to the plan for
Task1 and Task3?
- Follow-Ups:
- References:
- Re: Dependencies and out of sequence scenario.
- From: Mike Glen
- Re: Dependencies and out of sequence scenario.
- Prev by Date: Re: Elapsed duration
- Next by Date: Re: Project Unlock
- Previous by thread: Re: Dependencies and out of sequence scenario.
- Next by thread: Re: Dependencies and out of sequence scenario.
- Index(es):
Relevant Pages
|