Re: start time vs start date
- From: "Mike Glen" <glenATmvps.org>
- Date: Tue, 26 Sep 2006 20:11:44 +0100
Hi Shawnapolooza ,
Welcome to this Microsoft Project newsgroup :)
Tools/Options.../View tab and select a Date format to include the time.
FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :)
Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
wrote:
The start field for the tasks are only in dates, that doesn't help
for the project plan I'm creating, as many tasks are performed on the
same day, but at different times, so I need to know how to track the
start and end times instead of dates (e.g. task 1 is from 12:00-2:15,
task 2 is 2:15 to 2:40, task 3 is 2:40-3:05).
.
- Prev by Date: Re: Calulating fixed costs
- Next by Date: Re: More wrestling with units/resource allocation
- Previous by thread: Re: Calulating fixed costs
- Next by thread: Re: start time vs start date
- Index(es):
Relevant Pages
|