After making a gantt chart for an entire project, I paste the links to
a new project for each employee and print out calendar view schedules
for them. They prefer the ease of reading this view rather than a gantt
chart. I have 3 problems:

1. Split tasks don't show as split in calendar view, even though I see
a "split pattern" option under bar styles.

2. I can't find a way to stop the task bar for tasks that end on a
Friday from running over the weekend boxes. And, tasks that end on a
certain day spill over half day past the due date, causing confusion.

3. When I have too many linked tasks, the calendar simply won't show
them all, I assume because they are stacked and there isn't enough
space. Even when I change the font to 6 point so I can hand-move them,
I can't get them all to show.

Thanks for your time.
-Kate


--
sunrhat
------------------------------------------------------------------------
sunrhat's Profile: http://forums.techarena.in/member.php?userid=16964
View this thread: http://forums.techarena.in/showthread.php?t=575391

http://www.techarena.in

.



Relevant Pages

  • RE: Tailored calendar view in Project
    ... There are many more options in the Gantt chart view. ... Calendar view you can access through Format -> Bar Styles in the menu. ...
    (microsoft.public.project)
  • Re: Calendar View - show Multiple tasks
    ... Okay, what I *think* you have done is to go to the Calendar View, choose ... and open the Format> Bar Styles dialog box, ... you need to click after Name type a comma and type Resource ...
    (microsoft.public.project)
  • Re: Shading blocks of time in Gantt chart
    ... Make a new Calendar, call it "AA Calendar With School Holidays" (Tools, ... View, More Views, then just copy the Gantt Chart and call it, say "AA Gantt ... Chart With School Holidays". ... The answer was to change the block of time you wish to shade to ...
    (microsoft.public.project)
  • Re: Shading blocks of time in Gantt chart
    ... Make a new Calendar, call it "AA Calendar With School Holidays" ... View, More Views, then just copy the Gantt Chart and call it, say ... The answer was to change the block of time you wish to shade to ...
    (microsoft.public.project)
  • Re: Tailored calendar view in Project
    ... Sub Concatenate ... Then in the Calendar View, Format, Bar Styles, show Text1 instead of Name. ... About the closest thing to flagged fields is the "marked" task>> choice, but you only have the choice of formatting marked tasks differently. ... I'd like to set flags and display differently flagged>>> activities with different bar styles. ...
    (microsoft.public.project)