John,
I am not sure at this point why trees are dying. It is somthing that I need
to figure it out. Sorry!
Coming back to your latest advice, I have created a filter by using the
"flag" ("yes" or "No" but still the summary lines of interest are appearing
along with the directory!

I have an idea, maybe there is a way I be able to customize one of the
report templates in such that I can print the values of my cutomized text
columns?
I have tried to build the report format to deliver one table that is consist
of few customized texts and $ columns and I didn't have a good luck on it.
any ideat why I can't?
Thank you for your advise
"John" wrote:

In article <023AE233-F185-486A-B804-1363D78EFF91@xxxxxxxxxxxxx>,
Majid Sheikhan - ratiopharm
<MajidSheikhanratiopharm@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:

Hello John,
Thank you for the detailed information.
The problem is that unlinking the subprojects from master is a big
disadvantage for us becasue managers are constantly updating the single
project files not the master and that is due to security reason.
Let me explain the purpose of the master is to have all the projects
inforamtion consolidated into one file and we use the master to print the
report. Speaking about the report, one of the reprots is a summary that is
updatd along the first line of each project horizetally through custo,ized
columns and the problem is that in the master the first line is embeded under
the directory that it becomes the second line and in the master I need to
open it up in order to see the line. this will also kill more trees as well
becasue every first line of the table is empty.
maybe I should send you a sample file?
Please advise

Majid,
Please explain to me why trees are dying because of this.

Well, just of the top of my head, why not apply a filter to the master
so only the summary lines of interest (i.e. those at outline level 2)
appear. That way your report will not have any "empty" lines. Life will
be good and you and your managers can continue doing what you are doing.

If you have further questions, yes a sample of your file might be
helpful.

John
Project MVP
jensenj6atatcomcastdotdotnet
(remove obvious redundancies)

"John" wrote:

In article <F718CA5D-9283-427F-8DE9-BDDCDA9F6064@xxxxxxxxxxxxx>,
Majid Sheikhan - ratiopharm
<MajidSheikhanratiopharm@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:

Hello John,
Sorry for getting back to late.
I solved the problem of title and project name. I am adding it manually
Let me give you an example so that you can see my issue easily. I have
inserted 10 projects, now each project is hidden under its own subtask( +
sign next to it). So, now I have 10 subtask and when I open it you can
see
the names are duplicated. How can I consolidate all the inserted
projects
under one directory?
The problem is that, there are many customized columns and Managers are
already adding info into the columns on the very first line then save it.
Now, in the master schedule, the first line in the template becomes the
second line.
I hope I explained well.
Please advise
Majid

Majid,
Wow, I sure didn't remember this thread. I had to read it again to
remember what was said.

Well I think I understand but the terminology is still a little
confused. Basically what you have is a dynamically consolidated master.
The 10 subprojects are not physically part of the master however a
summary line is created in the master that holds a pointer to the actual
subproject. The contents of the subproject (all task rows under the
insertion point summary line) are indented under the summary line in the
master. Even though the sumbproject task lines are at outline level "2"
they cannot be outdented to outline level "1" in the master because they
are not part of the master. I know that probably sounds confusing but
that's the way it works.

The only way to get the subpprojects under one "directory" as you call
it (actually "directory" is a file attribute not a task attribute), is
to convert the dynamically consolidated master to a statically
consolidated master by unlinking the subproject from the master. Then
tasks, (the subprojects cease to be subprojects in a static master), can
be moved anywhere you like (e.g. indent/outdent).

I'm not sure what the customized fields has to do with anything but as I
stated above, tasks at outline level "1" in the subprojects will be at
outline level "2" in a dynamic master.

Now, I hope I explained it adequately.

John
Project MVP

"John" wrote:

In article <4FECE49F-7A85-4EE1-8598-17E81F602608@xxxxxxxxxxxxx>,
Majid Sheikhan - ratiopharm
<MajidSheikhanratiopharm@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:

Hello John,
Thank you for your advice.
Could that be possible to set by default the "title" be the "project
name"?
I tried it but not successful.
Majid

Majid,
It's not clear what you tried and its been a while since I delved into
this subject, however there have been discussions on this very issue in
this newsgroup perhaps a year ago. You might want to try a search.

As I recall, this is how it works, and the process is a little
different
depending on which version of Project you are using. This applies to
Project 2003. When a new Project file is created, Project will set the
Title to be the same as the filename. However if that file is edited
and
saved under a different name, the Title will remain (i.e. NOT change to
the new filename). However, the Title can be changed manually by the
user. This is basically what happens when you use a template file. But
here is the interesting part. Even if you change the Title of the
subproject and save the file, when you open your master, it will still
have the old Title at the insertion point summary line. In order to get
the new Title to show on the insertion point summary line, you will
need
to build a new master. How about that for "strangeness"?

I suggest the following. When your managers take the template and
create
their own file, have them change the Title to the new filename. Then
after all the subproject files are created, build your consolidated
master. Or, you could also manually change the Task Name at the
insertion point summary line in an already existing master - after all,
it's just a name. Neither approach is particularly convenient, but life
with Project isn't always easy.

Hope this helps.
John
Project MVP

"Majid Sheikhan - ratiopharm" wrote:

Hello Dear,
I have created a template file. project managers pick up the
template
and
rename it to a project and work on it. I insert each file into the
master
file.
Each time when I insert a project, it creates a subtask (a plus
sign
next
to
it) called "master draft" in the master.
I end up to have many "master draft" and within each of them there
is
one
project.
My question is how to insert a project without it
I hope I was clear
Thanks in advance





.



Relevant Pages

  • Re: inserted project hours out of sync
    ... One is the Duration field, ... If the schedule changes when the subprojects ... statically consolidated master file is a single individual file made up ... individual subprojects all have a Project Start Date of 5/1/06. ...
    (microsoft.public.project)
  • Re: Circular Reference - cannot locate
    ... some master tasks within some of the Master plans are defaulting to certain ... only way to rectify this is to completely rebuild the plan from scratch - I ... Whether or not this "insertion indenture" is ... so there are problems in individual subprojects. ...
    (microsoft.public.project)
  • Re: Consolidating projects
    ... It sounds like you may be talking about a shared resource pool file ... Even with a standard dynamically linked master file dates or constraints ... on tasks in one subproject have no effect on other subprojects UNLESS ... consolidate projects and keeping them independent. ...
    (microsoft.public.project)
  • Re: Master and Subprojects - Duplicate Tasks Entries in "Resource Usag
    ... Then when I try to close my Master it asks me again if I ... the subprojects, edits to tasks in those subprojects does in fact impact ... I'm still confused too if I should save my> Resource Pool file first? ... Can the action of halting the sharing cause duplicates? ...