Re: Tasks duration (errors?)
- From: Baby Dork <BabyDork@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Mon, 21 Aug 2006 12:52:01 -0700
Steve... I'm sorry to jump in during your conversation however; I have a
question concerning time entered. Most of my Projects last at least 10
years, are defined by multiple "Tiers" and have well over 250 tasks (per
Project) that have no commonalty within any of the task names.
Unfortunately, (maybe for me) the dates that I enter have to be reflected
EXACTLY the way I enter them (because “Uncle Sam” said so) - MSP cannot
calculate/recalculate them in anyway. With that said, what should be entered
as far as the "20" days worked within a month so that MSP doesn't change my
dates? Am I ___ out of luck?
It would be awesome if you could answer my next question as well (I have
faith in you Steve). One of the other problems that I'm experiencing has to
do with linking tasks between Projects. I’ve created a Master Project by
combining four separate Projects through importing (this was what someone
told me to do within this group). Many of my tasks are used multiple times,
which seems to confuse MSP when linking/grouping occurs (could be that I’m
confused as well). What I ultimately need is to be able to see only the
“Basic” overall Project when first viewed. If the person viewing the Project
needs further definition of a task, they should be able to “click” on an icon
(whatever) and all of the other tasks/subtasks that pertain to the first open
up below it. I hope this makes since.
"Sorry about the display name"
"Steve House [MVP]" wrote:
But what about February? or leap years? Given any arbitrary date, exactly.
1 calendar month later won't always be 22 working days later (or 20 or 21 or
any other number you might come up with). Why do you want to say that a
task lasts 4 calendar months anyway? In terms of predicting when it will
finish given the date it starts, the only thing that counts is the amount of
time a worker spends actively engaged in the task and calendar elapsed time
spans don't convey any information about productive time.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
"AB" <AB@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:FBC36810-C8BA-4752-BE55-FF13E1798419@xxxxxxxxxxxxxxxx
Steve, thank you for your answer.
I fully agree with what you say. My problem was that 20 working days
per months didn't match the rest of my project... I re-defined it to 22
(actually 21.72, without taking vacations and days off). So now when I
"say"
4 months, it actually shows 4 calendar months (or 88 working days).
Thanks again for your comments...
AB
"Steve House [Project MVP]" wrote:
The number of working days Project considers a "month" is set in the
Tools,
Options menu, Calendar page. The default is 20 days. So if you enter a
task's duration as "4 months" Project says that it is 80 working days.
At 8
hours per day that means the duration is 640 working hours. It then
begins
at the task's start date and time and counts off 640 working hours as
defined in the working time calendar to come up with the finish date.
Project's task durations should almost always measured and recorded in
working time hours instead of elapsed clock time hours. Think about it a
sec and you'll see why. The task only proceeds when someone is there
doing
it. If it will require 16 hours to complete it, will take more elapsed
time
to get it done when you only work on it in drips and drabs than if you
work
on it in one continuous block. The only thing that counts towards
completing it is the time you spend actively do it.
HTH
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
"AB" <AB@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:585E1604-9692-4838-860C-59CD04136B5F@xxxxxxxxxxxxxxxx
I have a task that I want to start on March 1st, 2007. I know it should
take
4 month... so I enter that too. Now, MS Project 2003 shows the end of
it
June 6th, 2007, while I was expecting it to be July the 1st. Why is it
doing
it? How many (working) days does Project assign to 'month'?
I had to put 17.4 weeks -- 52.14/12*4 = 17.4 (weeks-per-year /
months-per-year * 4 months) 365 days)/ (7 days/week)-- to get it
right,
but
I don't think this should be the right way to do it....
Thanks
- Follow-Ups:
- Re: Tasks duration (errors?)
- From: Steve House
- Re: Tasks duration (errors?)
- Prev by Date: Re: How can I capture vendor work and client work in separate colu
- Next by Date: Re: How can I capture vendor work and client work in separate colu
- Previous by thread: Custom Field for Summary Tasks
- Next by thread: Re: Tasks duration (errors?)
- Index(es):
Relevant Pages
|