Re: Ressource Cost in Task Usage View

Tech-Archive recommends: Fix windows errors by optimizing your registry



Hi John,

in fact I had read the FAQ several times before I wrote my posting.
Seems that the explanation was over my head... Thanks for your
re-iteration, I got it now.

Upsh


John schrieb:

In article <1155932196.234108.97460@xxxxxxxxxxxxxxxxxxxxxxxxxxx>,
"Upsh" <upsh@xxxxxxx> wrote:

Hi John,

I'm not sure if I got it:

a) The ressource cost data in the italic rows of my Task Usage View is
"assignment data" not the original "ressource data".
b) It is not possible to access assignment data from a formula.

Correct?

What is "assignment data"? Is it something like a pointer or link to
the original ressource data?

Why isn't it possible to combine task data and ressource data within
the same view?

Regards,
Upsh

Upsh,
Did you read the FAQ? Sometimes you have to read something several times
to get the full gist of the information. But, let me re-iterate a couple
of points.
a) The Task Usage view shows Task and Assignment data, there is no
resource data. Likewise the Resource Usage view show Resource and
Assignment data, there is no task data.
b) "Formulas are only available for task or resource spare fields - they
are not available for assignment spare fields." (A direct quote from the
FAQ).

What exactly is assignment data? It is the bridge between tasks and
resources. From a task viewpoint assignment data looks a lot like
resource data but it is not. And from a resource viewpoint assignment
data looks a lot like task data but it is not. Task data can exist by
itself as can resource data, but assignment data can only exist in the
presence of both a task and a resource. I know, that sounds a little
confusing but that's the way the Project database structure was set up -
way back when.

Why isn't it possible to combine task and resource data in a single
view? I don't really know but with the existence of assignment data the
two combination views (i.e. Task and Resource Usage) provide the
equivalent information. Some fields are shared and can be viewed in more
than one view type. For example, the Resource Initials field can be
viewed in a task view or a resource view. The Cost field can be shown in
any view type.

Hopefully I've explained it a little better. If you still have a
specific question, I'll be glad to help further.

John


John schrieb:

In article <1155903347.890824.149310@xxxxxxxxxxxxxxxxxxxxxxxxxxxx>,
"Upsh" <upsh@xxxxxxx> wrote:

Hi,

I tried to access ressource cost of a certain task - those rows that
are formatted in italic - from a formula in a custom field but that did
not work.

If I add the field "cost" each ressource row correctly displays the
cost per ressource. The task row correctly shows the sum of all
ressource cost per task.

If I add the custom field "Cost1" with a formula which consists of
nothing than "[Cost]" then the ressource rows show "0". In the task row
ressource cost are correctly summed.

Does anybody know how to access (single) ressource cost in Task Usage
View?

Regards,
Usph

Usph,
I think you might benefit by going to our MVP website at:
http://www.mvps.org/project/faqs.htm
and reading FAQ 51 - Data Types: Task, Resource and Assignments. Then if
you still have a question, post back.

John
Project MVP

.



Relevant Pages

  • Re: Ressource Cost in Task Usage View
    ... The ressource cost data in the italic rows of my Task Usage View is ... It is not possible to access assignment data from a formula. ... resource data. ...
    (microsoft.public.project)
  • Re: Ressource Cost in Task Usage View
    ... Actually I wrote that particular FAQ. ... The ressource cost data in the italic rows of my Task Usage View is ... It is not possible to access assignment data from a formula. ... resource data. ...
    (microsoft.public.project)
  • Re: Show a task custom fields in the Resource Usage form
    ... When you add a field (Text10) to the Resource Usage view and add data, ... The FAQ can be found at: ... for Assignment data, Resource Assignments and Task Assignment data. ...
    (microsoft.public.project)
  • Re: Filtering Tasks in Resource Usage View (Report)
    ... Resource filter, or if I use AutoFilter, Only the nodes of the hierarchy (the ... Assignment data bridges task and resource data. ... Each of these object types has several spare fields associated with it. ...
    (microsoft.public.project)
  • Re: Filtering Tasks in Resource Usage View (Report)
    ... The basic view shows each resource ... when I attempt to apply this filter to the resource view nothing ... Assignment data bridges task and resource data. ... Each of these object types has several spare fields associated with it. ...
    (microsoft.public.project)