Re: Resource Pool



Hi,

OK I did it myself, no more guesswork
You want a grouping by Resource, then by Project, not showing thae
assignment details?
I have it in front of me.

Group, New
Check On Group Assignments, not Resources (!!!!!VITAL)
Group by Name
Then by Project, Field type= assignment (VITAL)
OK, Apply

Show, Outline Level2

That's it, definitely, it's here before me

HTH


--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"Noetic" <Noetic@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
news:FA1CD9ED-D29D-4122-AA86-7288ACADB605@xxxxxxxxxxxxxxxx
Hi,

The Show/Hide Assignments button hide the name of the shared projects as
well and keeps the name of the resource pool only, I am looking to get the
names of the projects that is assigned to each resource without the tasks
for
each project, and it seemed that there is no way I can hide the tasks and
just keep the projects name, or may be I am doing it wrong!

"Jan De Messemaeker" wrote:

Hi,

The table is not a problem, just create it by inserting/deleting columns
or
by View, table, More Tables, Edit.

As for the level of detailm, sorry, I wasn't clear (euphemism for an
error)
You don't have to hid ethe details, but use the "Show/Hide Assignments"
button.
HTH

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"Noetic" <Noetic@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
news:06B7D165-FA0B-4B5E-8DA3-411F2147AFF5@xxxxxxxxxxxxxxxx
Thank you Jan.

I tried to group by projects and hide the details but it hides the
resources
as well, I need a table that would have the following columns: Names
without
detailed tasks ; projects, total work start,and finish.

Noetic





.



Relevant Pages

  • Re: Resource Usage by Task for Selected Tasks Only
    ... assignment) and I still get Asg1 when running the ShowTaskAssignmentdata ... the same data in the assignment custom field added to the Resource Usage ... Add the Text1 column to both Task and Resource Usage views. ...
    (microsoft.public.project)
  • Re: Formula problem in resource usage number field
    ... calculation for task+group summary rows: ... sums on resource level, ... some reason), no value on assignment level (sorry, I mistyped here in my last ...
    (microsoft.public.project)
  • Re: How can I track weighted future project needs?
    ... write formulas for the assignment row only on the resource row, ... can't calculate the weighed work per assignment. ... Project A 100% probability of award, Project B 50% probability, ... As your sales team gets closer to closing the sale, ...
    (microsoft.public.project)
  • Re: Multiple resources, varying units
    ... and put in the % values in the resource table, ... the formula works (duration * assignment = work). ... last two people are allocated at 100% assignment units. ...