Ressource Cost in Task Usage View
- From: "Upsh" <upsh@xxxxxxx>
- Date: 18 Aug 2006 05:15:47 -0700
Hi,
I tried to access ressource cost of a certain task - those rows that
are formatted in italic - from a formula in a custom field but that did
not work.
If I add the field "cost" each ressource row correctly displays the
cost per ressource. The task row correctly shows the sum of all
ressource cost per task.
If I add the custom field "Cost1" with a formula which consists of
nothing than "[Cost]" then the ressource rows show "0". In the task row
ressource cost are correctly summed.
Does anybody know how to access (single) ressource cost in Task Usage
View?
Regards,
Usph
.
- Follow-Ups:
- Re: Ressource Cost in Task Usage View
- From: John
- Re: Ressource Cost in Task Usage View
- Prev by Date: Re: different actual work and work entries in the task usage view?
- Next by Date: Re: Create a custom time scale?
- Previous by thread: Re: different actual work and work entries in the task usage view?
- Next by thread: Re: Ressource Cost in Task Usage View
- Index(es):
Relevant Pages
|