Re: Custom Field for Work Order #
- From: "Jan De Messemaeker" <jandemes at prom hyphen ade dot be>
- Date: Wed, 16 Aug 2006 09:20:13 +0200
Hi,
Not necssrily; it can be copied ito a property of the ASSIGNMENT and then
shows in both Usage views
--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"Rob Schneider" <honeycreek2006-guard@xxxxxxxxx> schreef in bericht
news:u5iDZbKwGHA.2204@xxxxxxxxxxxxxxxxxxxxxxx
Ah yes, that works, but it then becomes a property of the Resource, notthis
the Task ... Works for me though.
Mike Glen wrote:
Hi Dave,
Welcome to this Microsoft Project newsgroup :-)
You might like to see FAQ Item: 37 - Custom Fields in Tables. FAQs,
companion products and other useful Project information can be seen at
web address:http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on :-)
Mike Glen
Project MVP
Rob Schneider wrote:
Dave wrote:
I have inserted a custom field for tasks (number 1) for Work OrderThe Resource Usage view is a two-dimensional view of the resources and
#. THey can enter the work order # in this field in the gantt view.
I want to display this custom field in the resource usage view. Can
I do it and if so, how?
Thanks,
Dave
properties of those resources (plus a time dimension if you show it).
The Task Custom Field No. 1 is a property of Tasks, not of resources.
It's not possible to show this additional Task property on a view that
is specific to Resources.
.
- Follow-Ups:
- Re: Custom Field for Work Order #
- From: Rob Schneider
- Re: Custom Field for Work Order #
- References:
- Re: Custom Field for Work Order #
- From: Rob Schneider
- Re: Custom Field for Work Order #
- From: Mike Glen
- Re: Custom Field for Work Order #
- From: Rob Schneider
- Re: Custom Field for Work Order #
- Prev by Date: Re: project durations
- Next by Date: Re: Custom Field for Work Order #
- Previous by thread: Re: Custom Field for Work Order #
- Next by thread: Re: Custom Field for Work Order #
- Index(es):
Relevant Pages
|